Concept Data Center — Southside VA
$5.38B to deliver 457.2 MW of IT capacity
A 4-building program of 114.3 MW IT buildings in Southside, VA, NTP July 2027, with the last building ready for service in August 2030. Total development cost is $5.38B escalated — $4.69B of construction plus $0.69B of owner development costs and contingency.
What drives the number
- Electrical is 62% of direct cost ($572M per building) — 56 × 3 MW blocks with generators, unit substations and UPS; HVAC / cooling adds 18%.
- Indirects add 16.7% to direct cost ($155M per building): contingency, General Conditions, fee, insurance and bond.
- Pricing confidence: 65% of direct cost needs budget quotes / takeoff and 32% is allowance-based — these lines carry most of the estimate's range (−20% / +30%).
- Procurement is already on the critical path: 4 long-lead items back-schedule to order dates before the status date and 3 must be ordered now; 7 delivery-vs-readiness conflicts flagged on Building 1.
Program by building
| Building | Start | Midpoint | Site factor | Q4 2026 $ | Escalation | Escalated | $/IT MW |
|---|---|---|---|---|---|---|---|
| Building 1 | Jul 2027 | May 2028 | 1.00 | $1,079.0M | 1.060 | $1,144.2M | $10.01M |
| Building 2 | Jan 2028 | Nov 2028 | 0.80 | $1,071.8M | 1.082 | $1,159.3M | $10.14M |
| Building 3 | Jul 2028 | May 2029 | 0.80 | $1,071.8M | 1.103 | $1,182.1M | $10.34M |
| Building 4 | Jan 2029 | Nov 2029 | 0.80 | $1,071.8M | 1.125 | $1,205.7M | $10.55M |
| Construction — all buildings | $4,294.3M | $4,691.3M | $10.26M |
Owner's-rep KPIs (Building 1)
| KPI | Value | Typical range | Status |
|---|---|---|---|
| GC staffing as % of direct cost | 3.1% | 2% – 4% | In range |
| Craft per safety staff at peak | 123.1 | 50 – 100 : 1 (hyperscale owners often 1:50) | Thin |
| Staff to Volume (S/V) — fully burdened staff cost ÷ grand total | 2.6% | 2.0% – 4.0% | In range |
| Return on Staff (ROS) — fee ÷ fully burdened staff cost | 1.45x | 1.0x – 2.0x | In range |
| Earnings to Volume (E/V) — fee ÷ grand total | 3.8% | 2.5% – 4.0% | In range |
Basis of design
Concept Data Center is a 114.3 MW IT (142.9 MW facility load at a design PUE of 1.25) data center of 457,200 GSF on 2 levels, with a 900 × 254 ft footprint and a 66 ft height to parapet. It houses 880 rack positions at 130 kW per rack in 8 data halls of about 30,000 SF each, with 80% of IT heat removed by direct-to-chip liquid cooling. Construction duration is 20 months from NTP to ready for service.
Design criteria
- IT load and density
- 114.3 MW IT per building; 130 kW average per rack; 880 racks in 4 lineups per hall; 80% liquid / 20% air heat split (22,860 kW residual air load).
- Efficiency
- Design PUE 1.25 (facility load 142.9 MW). Air-cooled chillers with integral free cooling; elevated supply water temperatures for liquid cooling; energy code compliance per ASHRAE 90.4 as adopted locally.
- Electrical redundancy
- Block-redundant: 48 active blocks of 3 MW plus one reserve block per 6 (N + 1 per 6), 56 blocks in total. Each block: one 3,750 kVA unit substation, one LV main switchboard, one standby generator and UPS. Target concurrent maintainability (Uptime Tier III equivalent) — confirm against the tenant standard.
- Backup power and fuel
- Standby generation: 56 × 3.25 MW class natural gas generators. Pipeline gas through a site metering/regulating station and yard gas header; no on-site fuel storage. Confirm gas service firmness, pressure and code acceptance of pipeline fuel for standby use (slower load pickup puts more ride-through on the UPS).
- UPS and ride-through
- Static modular UPS at 1.25 × IT load (142,875 kW) so CDUs and critical pumps ride through on UPS; lithium-ion batteries at ~5 minutes; battery rooms per NFPA 855.
- Cooling redundancy
- Heat rejection 43,500 tons provided (87 × 500 t) vs 42,900 tons required (IT × 1.1 with N + 1 at 1.2). CDUs at N + 1 per 8 (52 × 2 MW). Size chillers for the local design ambient — derate for hot climates.
- Structure
- Steel frame (~6,860 tons, 0.015 t/GSF before seismic premium), composite deck at Level 2, spread footings and grade beams; floor loading per tenant standard. Seismic basis: Southside VA is low seismicity — typically Seismic Design Category A–B (central Virginia seismic zone; confirm site class and Risk Category IV requirements with the structural engineer and geotech). Seismic weight = 0, so every seismic factor is 1.00.
- Envelope
- Insulated precast wall panels (~70% of opaque wall) with insulated metal panels (~30%); TPO roof R-30 on 228,600 SF; 4,800 SF curtain wall at the entry; 15,360 SF of louvers to electrical and mechanical spaces.
- Fire and life safety
- Double-interlock preaction in data halls and electrical rooms (348,000 SF); wet-pipe sprinklers in support and galleries; clean agent in MMR / critical rooms; VESDA aspirating detection; leak detection at TCS and CDU areas; 2 fire pumps. Codes: IBC / IFC as adopted, NFPA 13, 72, 75 / 76 and 855.
- Security
- Anti-climb perimeter fence (4,260 LF), crash-rated vehicle gates, guardhouse, mantraps at data halls, access control, CCTV and intrusion detection to the owner's security standard.
- Site
- Building parcel of 26.9 acres (1520 × 770 ft): 350,100 SF equipment yards, 304,400 SF asphalt, stormwater detention, diverse MV and fiber duct banks, and a natural gas service lateral with M&R station.
- Commissioning
- Level 1–5 commissioning with factory witness tests on major electrical and mechanical equipment and integrated systems testing at full load with load banks before ready for service.
Building organization
- Building organization
- Linear plan, 900 ft long: a south electrical band (60 ft deep), central data halls (150 ft deep, 4 per floor, each about 200 ft wide), and a north mechanical gallery (44 ft deep). The west end holds the lobby, NOC, offices and support (60 ft); the east end holds loading, meet-me rooms and staging (40 ft).
- Space program
- Data halls 240,000 SF (52%); electrical 108,000 SF (24%); mechanical galleries 70,400 SF (15%); support, loading and MMR 38,800 SF (8%). Area check: 0 SF.
- Levels
- Level 1: 4 data halls, electrical band with UPS and switchboards, mechanical gallery with CDUs and pumps, lobby / NOC, loading dock and MMRs. Level 2: 4 data halls per floor stacked over Level 1 with matching electrical and mechanical bands; freight elevators (2 × 10,000 lb) serve the upper level.
- Equipment yards
- South yard: 56 generators and 56 unit substations in paired rows facing the electrical band. North yard: 87 air-cooled chillers. Equipment pads total about 113,300 SF.
- Data hall fit
- Each hall carries 4 rack lineups of about 84 ft with A/B overhead busway (6,700 LF), TCS supply/return to rack manifolds (9,400 LF stainless), hot-aisle containment and fan walls for residual air.
- Delivery and phasing
- NTP Jul 2027; 20-month build. Long-lead items (utility substation, generators, transformers, MV switchgear) are ordered ahead of NTP per the OFCI matrix (section 09); see section 08 for building cadence and phases.
Level 1 plan — data halls, electrical band, mechanical gallery
Space program (one building)
| Site | Value |
|---|---|
| Building parcel | 26.9 ac |
| Equipment yards | 350,100 SF |
| Asphalt paving | 304,400 SF |
| Security fence | 4,260 LF |
| Heat rejection provided | 43,500 t |
Concept massing — one typical building
Major equipment schedule — one building
| System | Equipment | Qty | Unit | Size / rating | Basis / redundancy | Procure |
|---|---|---|---|---|---|---|
| Electrical | Utility service / campus substation feed | 1 | LS | Sized for 142.9 MW facility load | Utility scope; diverse feeds per campus plan | OFOI |
| Electrical | MV switchgear lineups (A/B) | 8 | EA | 34.5 kV, A/B lineups (~40 MW each) | A/B (2N) MV distribution to blocks | OFCI |
| Electrical | Unit substation transformers | 56 | EA | 3,750 kVA, 34.5 kV – 480 V | One per block; N + 1 per 6 | OFCI |
| Electrical | LV main switchboards (one per block) | 56 | EA | 480 V main switchboard per block | One per block | OFCI |
| Electrical | Natural gas standby generators (3.25 MW class, lean-burn, enclosure) | 56 | EA | 3.25 MW class, natural gas | One per block; N + 1 per 6 | OFCI |
| Electrical | Transfer switches / paralleling | 56 | EA | Generator paralleling / transfer per block | One per block | OFCI |
| Electrical | UPS systems (static, modular) | 142,875 | kW | Static modular; 1.25 × IT load | Block-redundant; CDUs and pumps on UPS | OFCI |
| Electrical | UPS batteries (Li-ion, 5-min) | 142,875 | kW | Lithium-ion, ~5 minutes | NFPA 855 rooms | OFCI |
| Electrical | Floor PDUs (500 kVA) | 229 | EA | 500 kVA | A/B distribution | OFCI |
| Electrical | Overhead busway, high-amp (incl. tap-offs) | 6,700 | LF | High-amp, incl. tap-offs | A/B over every lineup | OFCI |
| Electrical | EPMS | 114.3 | MW | Meters and head-end | Integrated with BMS | CFCI |
| Mechanical | Air-cooled chillers w/ free cooling (installed) | 87 | EA | 500 tons each, integral free cooling | 43,500 t provided vs 42,900 t required | OFCI |
| Mechanical | Coolant distribution units (2 MW) | 52 | EA | 2 MW each | N + 1 per 8 | OFCI |
| Mechanical | Hydronic pumps with VFDs | 58 | EA | Primary / process CHW | Duty / standby pairs | CFCI |
| Mechanical | Buffer / thermal storage tanks | 4 | EA | Buffer volume for ride-through | Sized with UPS ride-through | CFCI |
| Mechanical | Fan walls / CRAH for residual air | 22,860.0 | kW | Residual air cooling | 20% of IT heat to air | CFCI |
| Mechanical | DOAS / makeup air | 6 | EA | Ventilation and humidity control | N + 1 | CFCI |
| Mechanical | TCS stainless piping to lineups | 9,400 | LF | Stainless technology cooling loop | Supply / return per lineup | CFCI |
| Mechanical | Rack manifolds & quick-disconnects | 880 | EA | One per rack | Split per OFCI Matrix (often tenant) | See OFCI |
| Fire / life safety | Fire pumps & controllers | 2 | EA | Electric, with controllers | Per NFPA 20 | CFCI |
| Fire / life safety | Double-interlock preaction (halls, electrical) | 348,000 | SF | Halls and electrical rooms | With nitrogen generators | CFCI |
| Fire / life safety | VESDA aspirating smoke detection | 348,000 | SF | Aspirating smoke detection | Early warning | CFCI |
| Conveying | Heavy freight elevators (10,000 lb) | 2 | EA | 10,000 lb | IT and equipment moves | CFCI |
| Controls / IT | BMS / controls | 25,200 | PT | BMS points | Redundant servers / network | CFCI |
| Controls / IT | Meet-me rooms / entrance facilities | 2 | EA | Diverse carrier entrances | Two MMRs | CFCI |
| Site | Natural gas service lateral & metering/regulating station | 1 | LS | Lateral + metering / regulating station | Gas generators only | OFOI |
$924.2M direct cost per building
| Div | Description | Cost | $/GSF | $/IT MW | % direct |
|---|---|---|---|---|---|
| 01 | General Requirements | $25,532,354 | $55.85 | $223K | 2.8% |
| 02 | Existing Conditions | $250,000 | $0.55 | $2K | 0.0% |
| 03 | Concrete | $22,520,967 | $49.26 | $197K | 2.4% |
| 04 | Masonry | $3,078,000 | $6.73 | $27K | 0.3% |
| 05 | Metals | $56,948,200 | $124.56 | $498K | 6.2% |
| 06 | Wood, Plastics & Composites | $632,880 | $1.38 | $6K | 0.1% |
| 07 | Thermal & Moisture Protection | $9,528,899 | $20.84 | $83K | 1.0% |
| 08 | Openings | $4,140,200 | $9.06 | $36K | 0.4% |
| 09 | Finishes | $4,790,440 | $10.48 | $42K | 0.5% |
| 10 | Specialties | $650,000 | $1.42 | $6K | 0.1% |
| 11 | Equipment | $228,000 | $0.50 | $2K | 0.0% |
| 12 | Furnishings | $150,000 | $0.33 | $1K | 0.0% |
| 13 | Special Construction | $998,640 | $2.18 | $9K | 0.1% |
| 14 | Conveying Equipment | $2,400,000 | $5.25 | $21K | 0.3% |
| 21 | Fire Suppression | $7,102,600 | $15.53 | $62K | 0.8% |
| 22 | Plumbing | $2,757,680 | $6.03 | $24K | 0.3% |
| 23 | HVAC / Cooling | $164,822,520 | $360.50 | $1,442K | 17.8% |
| 25 | Integrated Automation | $6,552,000 | $14.33 | $57K | 0.7% |
| 26 | Electrical | $572,302,491 | $1,251.76 | $5,007K | 61.9% |
| 27 | Communications | $8,268,640 | $18.09 | $72K | 0.9% |
| 28 | Electronic Safety & Security | $7,999,960 | $17.50 | $70K | 0.9% |
| 31 | Earthwork | $4,039,246 | $8.83 | $35K | 0.4% |
| 32 | Exterior Improvements | $6,389,911 | $13.98 | $56K | 0.7% |
| 33 | Utilities | $12,077,525 | $26.42 | $106K | 1.3% |
| Direct cost subtotal | $924,161,153 | $2,021.35 | $8,085K | 100.0% |
$154.8M of indirects — 16.7% on direct
| Indirect | Amount | % of direct | $/GSF |
|---|---|---|---|
| Direct cost subtotal | $924,161,153 | 100.00% | $2,021.35 |
| Construction contingency | $46,208,058 | 5.00% | $101.07 |
| Subcontractor default insurance (SDI) | $8,986,288 | 0.97% | $19.66 |
| General Conditions | $28,228,525 | 3.05% | $61.74 |
| OCIP | $15,113,760 | 1.64% | $33.06 |
| Other insurance by GC | $5,113,489 | 0.55% | $11.18 |
| GC payment & performance bond | $8,222,490 | 0.89% | $17.98 |
| GC preconstruction fee | $2,000,000 | 0.22% | $4.37 |
| Fee | $40,923,334 | 4.43% | $89.51 |
| Indirect cost subtotal | $154,795,944 | 16.75% | $338.57 |
| Grand total — one building | $1,078,957,097 | $2,359.92 |
Estimate confidence
| Rating | Meaning | Direct cost | Share |
|---|---|---|---|
| High | common unit ranges | $36,237,409 | 3.9% |
| Medium | needs budget quote / takeoff | $596,693,744 | 64.6% |
| Low | allowance or scope-dependent | $291,230,000 | 31.5% |
Total development cost $5.38B
Building 1 carries the full estimate. Buildings 2–4 repeat it with a site development factor of 0.80, are escalated at 4.0% per year to each construction midpoint, and carry owner soft costs and contingency.
| Line | Rate / input | Basis | Amount (escalated) |
|---|---|---|---|
| Construction — all buildings | — | From table above | $4,691,261,252 |
| Campus-wide infrastructure (substations, MV backbone, roads, water / sewer, on-site generation) | — | Enter from the Campus Conceptual Estimate or owner budget ($) | $0 |
| Design & engineering (A/E, MEP, structural, civil) | 5.00% | % of construction | $234,563,063 |
| Owner's program / construction management | 1.50% | % of construction | $70,368,919 |
| Commissioning agent (L1–L5) | 0.75% | % of construction | $35,184,459 |
| Permits, fees, testing & inspections (owner-held) | 1.00% | % of construction | $46,912,613 |
| Legal, insurance, financing & other owner costs | 1.00% | % of construction | $46,912,613 |
| Land | — | Enter owner's land cost ($) — reference | $0 |
| Subtotal before owner contingency | — | $5,125,202,918 | |
| Owner's development contingency | 5.00% | % of subtotal, excluding land — scope growth, tenant changes, market risk | $256,260,146 |
| Total project development cost | escalated, excl. IT equipment | $5,381,463,064 |
Program spend peaks at $242M a month
Program — annual spend (escalated $)
| Year | Construction | Development | Total | Cumulative | % of program | Bldg starts |
|---|---|---|---|---|---|---|
| 2025 | $0.0M | $11.5M | $11.5M | $11.5M | 0.2% | 0 |
| 2026 | $0.0M | $69.4M | $69.4M | $81.0M | 1.3% | 0 |
| 2027 | $71.5M | $157.6M | $229.0M | $310.0M | 4.3% | 1 |
| 2028 | $1,769.8M | $217.2M | $1,986.9M | $2,297.0M | 36.9% | 2 |
| 2029 | $2,292.5M | $172.4M | $2,464.9M | $4,761.8M | 45.8% | 1 |
| 2030 | $557.5M | $62.1M | $619.6M | $5,381.5M | 11.5% | 0 |
| Total | $4,691.3M | $690.2M | $5,381.5M | 4 |
Building 1 — construction cash flow (Q4 2026 $, before retainage)
NTP Jul 2027 · Building 1 RFS Feb 2029 · last RFS Aug 2030
Campus program
Building 1 — key activities & milestones
4 items past their order-by date, 3 to order now
Order-by dates are back-scheduled from each item's Building 1 install start (install − ROS buffer − transit − lead time − submittals − bid / award). Status date Nov 13, 2026.
| ID | System / equipment | Type | Qty | Lead (wks) | PO / order by | Required on site | Flag |
|---|---|---|---|---|---|---|---|
| U-01 | Utility substation & revenue metering (campus feed) | OFOI | 1 LS | 104 | Oct 08, 2025 | Oct 06, 2027 | PAST — confirm slot |
| E-03 | Unit substation transformers 3,750 kVA (56) | OFCI | 56 | 80 | Mar 31, 2026 | Jan 04, 2028 | PAST — confirm slot |
| E-01 | Natural gas generators 3.25 MW, enclosed (56) | OFCI | 56 | 80 | Apr 07, 2026 | Jan 04, 2028 | PAST — confirm slot |
| E-02 | MV switchgear 34.5 kV (main / ring) | OFCI | 6 | 70 | Jul 15, 2026 | Feb 02, 2028 | PAST — confirm slot |
| U-02 | Natural gas service & meter set | OFOI | 1 LS | 40 | Nov 13, 2026 | Aug 20, 2027 | Order now |
| M-01 | Air-cooled chillers 500 t (87) | OFCI | 87 | 44 | Dec 29, 2026 | Jan 04, 2028 | Order now |
| E-04 | LV switchboards / paralleling gear | OFCI | 56 | 45 | Jan 13, 2027 | Feb 02, 2028 | Order now |
| E-10 | MV cable 35 kV & terminations | CFCI | LS | 30 | Apr 27, 2027 | Jan 18, 2028 | OK |
| E-05 | UPS modules (static, modular) | OFCI | 56 | 36 | May 01, 2027 | Mar 04, 2028 | OK |
| M-02 | CDUs 2 MW (liquid cooling) | OFCI | 52 | 32 | Jun 12, 2027 | Mar 18, 2028 | OK |
| S-03 | Elevators (freight) | CFCI | 2 | 40 | Jun 17, 2027 | May 18, 2028 | OK |
| E-06 | Li-ion battery cabinets | OFCI | 56 | 30 | Aug 19, 2027 | May 18, 2028 | OK |
| E-08 | Overhead busway, high-amp | OFCI | 6,700 LF | 26 | Aug 23, 2027 | Apr 17, 2028 | OK |
| E-07 | PDUs / RPPs | OFCI | 112 | 24 | Sep 06, 2027 | Apr 17, 2028 | OK |
| L-05 | Access control & CCTV head-end | OFOI | LS | 16 | Feb 22, 2028 | Jul 18, 2028 | OK |
| I-02 | Meet-me room carrier equipment | OFOI | LS | 20 | Apr 23, 2028 | Sep 17, 2028 | OK |
| M-04 | Rack manifolds, hoses, quick disconnects | OFOI | 880 | 20 | May 19, 2028 | Nov 17, 2028 | OK |
| I-01 | Server racks & IT equipment | OFOI | 880 | 30 | Jun 08, 2028 | Jan 18, 2029 | OK |
| E-09 | Busway tap-off boxes to racks | OFOI | 880 | 16 | Jun 16, 2028 | Nov 17, 2028 | OK |
Peak program staff 293 — 250 GC, 43 owner
GC staffing KPIs — Building 1 (peak craft 1,600, safety 1:125)
| KPI | Value | Typical range | Status |
|---|---|---|---|
| 1. GC staffing as % of direct cost | 3.1% | 2% – 4% | In range |
| 2. General Conditions + General Requirements as % of direct cost | 5.8% | 5% – 9% | In range |
| 3. Craft per GC staff at peak | 20.4 | 15 – 25 : 1 | In range |
| 4. Craft per superintendent at peak (excl. assistant supers) | 114.3 | 75 – 125 : 1 | In range |
| 5. Craft per safety staff at peak | 123.1 | 50 – 100 : 1 (hyperscale owners often 1:50) | Thin |
| 6. Field share of staff at peak (field, safety, QA/QC, Cx) | 66.2% | 60% – 70% | In range |
| 7. GC staffing cost per IT MW | $246,969 | Compare across buildings / bids | — |
| 8. Put-in-place per GC staff, peak month | $1,509,276 | $1.0M – $2.0M / month | In range |
| 9. Staff to Volume (S/V) — fully burdened staff cost ÷ grand total | 2.6% | 2.0% – 4.0% | In range |
| 10. Return on Staff (ROS) — fee ÷ fully burdened staff cost | 1.45x | 1.0x – 2.0x | In range |
| 11. Earnings to Volume (E/V) — fee ÷ grand total | 3.8% | 2.5% – 4.0% | In range |
Safety staffing scenarios (Building 1)
| Safety ratio | Safety staff | Added vs 1:125 | Added cost | GC total |
|---|---|---|---|---|
| 1 : 125 | 13 | 0 | $0 | $28,228,525 |
| 1 : 100 | 16 | 3 | $899,100 | $29,127,625 |
| 1 : 75 | 22 | 9 | $2,697,300 | $30,925,825 |
| 1 : 50 | 32 | 19 | $5,694,300 | $33,922,825 |
The same building in 13 markets
Building 1 re-priced line by line with market labor, material and seismic adjustments — same design, quantities and schedule. Order-of-magnitude reference only; location factors are planning assumptions, not quotes.
| Market | Electrician $/hr | Location factor | $/GSF | Per building | Per IT MW | Rank |
|---|---|---|---|---|---|---|
| Southside VA (base) | $26.35 | 1.000 | $2,360 | $1,079M | $9.44M | 1 |
| Atlanta, GA | $27.75 | 1.015 | $2,394 | $1,095M | $9.58M | 2 |
| Dallas–Fort Worth, TX | $28.56 | 1.023 | $2,414 | $1,104M | $9.66M | 3 |
| Dallas, TX (city / Dallas–Plano–Irving) | $29.71 | 1.035 | $2,442 | $1,117M | $9.77M | 4 |
| Phoenix, AZ | $30.22 | 1.047 | $2,471 | $1,130M | $9.89M | 5 |
| Columbus, OH | $31.11 | 1.049 | $2,476 | $1,132M | $9.91M | 6 |
| Las Vegas / Reno, NV | $30.45 | 1.074 | $2,534 | $1,159M | $10.14M | 7 |
| Salt Lake City, UT | $30.82 | 1.095 | $2,585 | $1,182M | $10.34M | 8 |
| New York / NJ | $38.75 | 1.164 | $2,747 | $1,256M | $10.99M | 9 |
| Northern Virginia (Ashburn) | $41.68 | 1.166 | $2,751 | $1,258M | $11.01M | 10 |
| Portland / Hillsboro, OR | $42.85 | 1.232 | $2,907 | $1,329M | $11.63M | 11 |
| Chicago, IL | $49.00 | 1.249 | $2,947 | $1,347M | $11.79M | 12 |
| Silicon Valley (San Jose), CA | $48.55 | 1.308 | $3,086 | $1,411M | $12.34M | 13 |
Southern Virginia: 7 campuses, 5,400 MW tracked
Comparables for this 457 MW program: Google Botetourt County (300 (est.) MW, under construction); Microsoft Boydton Campus (Azure East US) (1,100 MW, operational).
Campuses in the Southern Virginia market
| Campus | Operator | City | Status | MW | Notes |
|---|---|---|---|---|---|
| STACK Southern Virginia Megasite (Berry Hill) | STACK Infrastructure | Berry Hill (Pittsylvania Co., near Danville) | Planned | 3,000 | $100B / 30 yrs; 21 bldgs on ~1,733 ac; 2 on-site gas plants; early grading of ~400 ac approved Oct 2026; construction Q3 2027; 299 MW min load by … |
| Microsoft Boydton Campus (Azure East US) | Microsoft | Boydton | Operational | 1,100 | $2B+ since 2010; expanded repeatedly |
| Microsoft Panhandle Road Expansion | Microsoft | Boydton | Planned | 300 (est.) | 490 ac, 3 bldgs; filed Jun 2026 |
| Microsoft AVC17 Lakeside | Microsoft | Clarksville | Planned | 300 (est.) | 259 ac, 3 bldgs; permits filed 2022 |
| Google Botetourt County | Daleville | Under construction | 300 (est.) | Grading started 2026; air-cooled design | |
| Microsoft Tunstall Road | Microsoft | South Hill | Planned | 200 (est.) | 132 ac greenfield, 3 bldgs; permits filed 2022 |
| Ringgold Campus (Route 58 East) | Anchorstone Advisors | Ringgold (Pittsylvania Co.) | Planned | 200 | 946 ac; rezoning approved unanimously Jul 2026 |
General contractors — Southern Virginia first, then rest of VA
| GC | Campus | Market | Role | Confidence |
|---|---|---|---|---|
| No GCs recorded in Southern Virginia — nearest VA markets below. | ||||
| DPR Construction | Digital Realty Digital Loudoun Plaza | Northern Virginia | GC (Loudoun Exchange campus bldgs A,B,D,F,G,K) | confirmed |
| HITT Contracting | Digital Realty Manassas Campus | Northern Virginia | GC (Brickyard first building, 36 MW) | confirmed |
| DPR Construction | QTS Ashburn 1 & 2 | Northern Virginia | Construction manager (Ashburn-Shellhorn) | confirmed |
| HITT Contracting | Aligned IAD-01 Ashburn | Northern Virginia | GC (named for IAD-02 on same Ashburn campus) | confirmed |
| Clark Construction | NTT VA1–VA7 Ashburn | Northern Virginia | GC (VA6 and later Ashburn buildings) | confirmed |
| DPR Construction | Meta Henrico Data Center | Richmond | GC / builder (DPR project page) | confirmed |
Contested-site flags — Southern Virginia and VA
No contest entries for Southern Virginia or VA in this Atlas copy.
Developer portfolio signals (Beale, Related Digital, 5C) — VA
No Beale, Related Digital or 5C campuses recorded in VA.
7 schedule conflicts and 8 assumptions to confirm
Building 1 coordination checks — delivery vs readiness
| Check | Result |
|---|---|
| Generators ROS vs equipment pads | CONFLICT — 12 wks early |
| Transformers ROS vs equipment pads | CONFLICT — 12 wks early |
| Chillers ROS vs equipment pads | CONFLICT — 12 wks early |
| MV switchgear ROS vs dry-in | CONFLICT — 26 wks early |
| LV switchboards ROS vs dry-in | CONFLICT — 26 wks early |
| UPS ROS vs dry-in | CONFLICT — 21 wks early |
| CDUs ROS vs dry-in | CONFLICT — 19 wks early |
| Generator start-up (set finish) vs first gas | OK |
| L4 start vs permanent utility power | OK |
Assumptions to confirm
| Owner / tenant design standard | Redundancy (block-redundant, N+1 per 6), 130 kW racks, 80% liquid cooling and PUE 1.25 are template defaults. |
| Standby fuel | Natural gas generation — confirm service firmness, pressure and AHJ acceptance for standby use. |
| Campus infrastructure & land | Carried at $0 — enter the owner's substation, MV backbone, on-site generation and land figures. |
| Escalation | 4.0% / yr from the Q4 2026 pricing date to each building midpoint. |
| Repetition & site factors | Site development factor 0.80; repetition factor 1.00; full GC team per building. |
| Owner procurement | OFCI equipment lead times and ROS dates assume owner supply agreements — confirm manufacturing slots for items flagged PAST. |
| Utility power | Permanent power and first gas dates are schedule inputs; utility energization gates Level 4 / 5 commissioning. |
| Labor market | Peak craft of 1,600 and 40% imported staff — validate against competing regional work. |
Basis, exclusions and limitations
Classification
This is a conceptual, planning-level estimate consistent with AACE International Class 4 (feasibility / concept screening), with an expected accuracy range of roughly −20% / +30% around the point estimate. Building 1 is priced in Q4 2026 dollars; program totals are escalated to each building's construction midpoint.
Method
- Quantities are derived from the concept massing (footprint, levels, equipment counts) and priced by CSI MasterFormat division with installed unit costs, each carrying a basis note and a confidence rating.
- General Conditions are built from a position-by-position GC staffing plan; General Requirements, contingency, insurance, bond and fee are carried as itemized indirects.
- Cash flow is cost-loaded by line item and sequence of operations; procurement dates are back-scheduled from installation needs.
- Unit prices are planning-level ranges cross-checked against published industry benchmarks and labor wage data. They are not vendor quotes, subcontractor bids or licensed cost-database prices.
Exclusions
Land; campus-wide infrastructure (mass grading, campus roads, substations, campus MV, on-site gas generation / central power plant); tenant IT (servers, racks, network cabling to racks); financing; Virginia sales & use tax (owner equipment may qualify for the VA data center exemption — confirm eligibility); prevailing-wage requirements; hazardous materials; rock excavation beyond the ground improvement allowance. Escalation and owner soft costs are carried only in the program total (section 06).
Limitations
Prepared by
Frank Fernandez · Owner's Representation · Mission Critical
Capitol Construction Management · capitolcm.com
Programmatic Builder is proprietary to Frank Fernandez, developed for Capitol Construction Management. © 2026 Frank Fernandez. Sample report — illustrates a concept program; not a real project.