Capitol/CM Sample report · Concept Program Report — Southside VA 4 × 114 MW All sample reports View only
Capitol/CMSample report
Concept Program Report · AACE Class 4

Concept Data Center — Southside VA

4 × 114.3 MW IT hyperscale data center program · Southside, VA · natural gas standby generation
Total development cost
$5.38B
escalated · excl. IT equipment
Program IT capacity
457.2 MW
4 buildings · 1,828,800 GSF
Building 1
$1,079.0M
$9.44M / MW · $2,360 / GSF
Schedule
Jul 2027
NTP → last RFS Aug 2030
Prepared by Frank Fernandez · Capitol Construction ManagementPricing basis Q4 2026 $ · Report date Nov 19, 2026
Capitol/CMSample report · Programmatic Builder · Concept Data Center — Southside VAClient edition
Executive summary

$5.38B to deliver 457.2 MW of IT capacity

A 4-building program of 114.3 MW IT buildings in Southside, VA, NTP July 2027, with the last building ready for service in August 2030. Total development cost is $5.38B escalated — $4.69B of construction plus $0.69B of owner development costs and contingency.

Development $ / IT MW
$11.77M
$2,943 / GSF
Construction (escalated)
$4.69B
$10.26M / IT MW
Building 1 (Q4 2026 $)
$1,079M
$9.44M / MW · $2,360 / GSF
Escalation carried
$397M
4.0% / yr to midpoint

What drives the number

  • Electrical is 62% of direct cost ($572M per building) — 56 × 3 MW blocks with generators, unit substations and UPS; HVAC / cooling adds 18%.
  • Indirects add 16.7% to direct cost ($155M per building): contingency, General Conditions, fee, insurance and bond.
  • Pricing confidence: 65% of direct cost needs budget quotes / takeoff and 32% is allowance-based — these lines carry most of the estimate's range (−20% / +30%).
  • Procurement is already on the critical path: 4 long-lead items back-schedule to order dates before the status date and 3 must be ordered now; 7 delivery-vs-readiness conflicts flagged on Building 1.

Program by building

BuildingStartMidpointSite factorQ4 2026 $EscalationEscalated$/IT MW
Building 1Jul 2027May 20281.00$1,079.0M1.060$1,144.2M$10.01M
Building 2Jan 2028Nov 20280.80$1,071.8M1.082$1,159.3M$10.14M
Building 3Jul 2028May 20290.80$1,071.8M1.103$1,182.1M$10.34M
Building 4Jan 2029Nov 20290.80$1,071.8M1.125$1,205.7M$10.55M
Construction — all buildings$4,294.3M$4,691.3M$10.26M

Owner's-rep KPIs (Building 1)

KPIValueTypical rangeStatus
GC staffing as % of direct cost3.1%2% – 4%In range
Craft per safety staff at peak123.150 – 100 : 1 (hyperscale owners often 1:50)Thin
Staff to Volume (S/V) — fully burdened staff cost ÷ grand total2.6%2.0% – 4.0%In range
Return on Staff (ROS) — fee ÷ fully burdened staff cost1.45x1.0x – 2.0xIn range
Earnings to Volume (E/V) — fee ÷ grand total3.8%2.5% – 4.0%In range
© 2026 Frank Fernandez · Programmatic Builder developed for Capitol Construction Management · capitolcm.com  |  Sample report — concept program, not a real project · Concept estimate (AACE Class 4) · Not a quote02
Capitol/CMSample report · Programmatic Builder · Concept Data Center — Southside VADesign basis
01 · Program & design basis

Basis of design

Concept Data Center is a 114.3 MW IT (142.9 MW facility load at a design PUE of 1.25) data center of 457,200 GSF on 2 levels, with a 900 × 254 ft footprint and a 66 ft height to parapet. It houses 880 rack positions at 130 kW per rack in 8 data halls of about 30,000 SF each, with 80% of IT heat removed by direct-to-chip liquid cooling. Construction duration is 20 months from NTP to ready for service.

IT / facility load
114.3 MW
142.9 MW facility · PUE 1.25
Gross area
457,200
GSF · 2 levels · 900 × 254 ft
Racks
880
130 kW avg · 80% liquid
Power blocks
56
3 MW · N+1 per 6

Design criteria

IT load and density
114.3 MW IT per building; 130 kW average per rack; 880 racks in 4 lineups per hall; 80% liquid / 20% air heat split (22,860 kW residual air load).
Efficiency
Design PUE 1.25 (facility load 142.9 MW). Air-cooled chillers with integral free cooling; elevated supply water temperatures for liquid cooling; energy code compliance per ASHRAE 90.4 as adopted locally.
Electrical redundancy
Block-redundant: 48 active blocks of 3 MW plus one reserve block per 6 (N + 1 per 6), 56 blocks in total. Each block: one 3,750 kVA unit substation, one LV main switchboard, one standby generator and UPS. Target concurrent maintainability (Uptime Tier III equivalent) — confirm against the tenant standard.
Backup power and fuel
Standby generation: 56 × 3.25 MW class natural gas generators. Pipeline gas through a site metering/regulating station and yard gas header; no on-site fuel storage. Confirm gas service firmness, pressure and code acceptance of pipeline fuel for standby use (slower load pickup puts more ride-through on the UPS).
UPS and ride-through
Static modular UPS at 1.25 × IT load (142,875 kW) so CDUs and critical pumps ride through on UPS; lithium-ion batteries at ~5 minutes; battery rooms per NFPA 855.
Cooling redundancy
Heat rejection 43,500 tons provided (87 × 500 t) vs 42,900 tons required (IT × 1.1 with N + 1 at 1.2). CDUs at N + 1 per 8 (52 × 2 MW). Size chillers for the local design ambient — derate for hot climates.
Structure
Steel frame (~6,860 tons, 0.015 t/GSF before seismic premium), composite deck at Level 2, spread footings and grade beams; floor loading per tenant standard. Seismic basis: Southside VA is low seismicity — typically Seismic Design Category A–B (central Virginia seismic zone; confirm site class and Risk Category IV requirements with the structural engineer and geotech). Seismic weight = 0, so every seismic factor is 1.00.
Envelope
Insulated precast wall panels (~70% of opaque wall) with insulated metal panels (~30%); TPO roof R-30 on 228,600 SF; 4,800 SF curtain wall at the entry; 15,360 SF of louvers to electrical and mechanical spaces.
Fire and life safety
Double-interlock preaction in data halls and electrical rooms (348,000 SF); wet-pipe sprinklers in support and galleries; clean agent in MMR / critical rooms; VESDA aspirating detection; leak detection at TCS and CDU areas; 2 fire pumps. Codes: IBC / IFC as adopted, NFPA 13, 72, 75 / 76 and 855.
Security
Anti-climb perimeter fence (4,260 LF), crash-rated vehicle gates, guardhouse, mantraps at data halls, access control, CCTV and intrusion detection to the owner's security standard.
Site
Building parcel of 26.9 acres (1520 × 770 ft): 350,100 SF equipment yards, 304,400 SF asphalt, stormwater detention, diverse MV and fiber duct banks, and a natural gas service lateral with M&R station.
Commissioning
Level 1–5 commissioning with factory witness tests on major electrical and mechanical equipment and integrated systems testing at full load with load banks before ready for service.
© 2026 Frank Fernandez · Programmatic Builder developed for Capitol Construction Management · capitolcm.com  |  Sample report — concept program, not a real project · Concept estimate (AACE Class 4) · Not a quote03
Capitol/CMSample report · Programmatic Builder · Concept Data Center — Southside VADesign basis
01 · Program & design basis

Building organization

Building organization
Linear plan, 900 ft long: a south electrical band (60 ft deep), central data halls (150 ft deep, 4 per floor, each about 200 ft wide), and a north mechanical gallery (44 ft deep). The west end holds the lobby, NOC, offices and support (60 ft); the east end holds loading, meet-me rooms and staging (40 ft).
Space program
Data halls 240,000 SF (52%); electrical 108,000 SF (24%); mechanical galleries 70,400 SF (15%); support, loading and MMR 38,800 SF (8%). Area check: 0 SF.
Levels
Level 1: 4 data halls, electrical band with UPS and switchboards, mechanical gallery with CDUs and pumps, lobby / NOC, loading dock and MMRs. Level 2: 4 data halls per floor stacked over Level 1 with matching electrical and mechanical bands; freight elevators (2 × 10,000 lb) serve the upper level.
Equipment yards
South yard: 56 generators and 56 unit substations in paired rows facing the electrical band. North yard: 87 air-cooled chillers. Equipment pads total about 113,300 SF.
Data hall fit
Each hall carries 4 rack lineups of about 84 ft with A/B overhead busway (6,700 LF), TCS supply/return to rack manifolds (9,400 LF stainless), hot-aisle containment and fan walls for residual air.
Delivery and phasing
NTP Jul 2027; 20-month build. Long-lead items (utility substation, generators, transformers, MV switchgear) are ordered ahead of NTP per the OFCI matrix (section 09); see section 08 for building cadence and phases.

Level 1 plan — data halls, electrical band, mechanical gallery

Space program (one building)

2026-11-19T10:36:21.997750 image/svg+xml Matplotlib v3.11.2, https://matplotlib.org/ 0K 50K 100K 150K 200K 250K 300K Support / MMR Mechanical Electrical Data halls 38,800 SF · 8% 70,400 SF · 15% 108,000 SF · 24% 240,000 SF · 52%
SiteValue
Building parcel26.9 ac
Equipment yards350,100 SF
Asphalt paving304,400 SF
Security fence4,260 LF
Heat rejection provided43,500 t
© 2026 Frank Fernandez · Programmatic Builder developed for Capitol Construction Management · capitolcm.com  |  Sample report — concept program, not a real project · Concept estimate (AACE Class 4) · Not a quote04
Capitol/CMSample report · Programmatic Builder · Concept Data Center — Southside VAMassing
02 · Concept massing study

Concept massing — one typical building

Overall building, viewed from the southwest: 56 natural gas generators and unit substations in the south yard, 87 air-cooled chillers in the north yard.
Site plan — 1,520 × 770 ft parcel, utility entries, parking, truck court and stormwater.
Construction logistics — haul roads, laydown, temporary facilities and crane access.
© 2026 Frank Fernandez · Programmatic Builder developed for Capitol Construction Management · capitolcm.com  |  Sample report — concept program, not a real project · Concept estimate (AACE Class 4) · Not a quote05
Capitol/CMSample report · Programmatic Builder · Concept Data Center — Southside VAEquipment
03 · Major equipment

Major equipment schedule — one building

SystemEquipmentQtyUnitSize / ratingBasis / redundancyProcure
ElectricalUtility service / campus substation feed1LSSized for 142.9 MW facility loadUtility scope; diverse feeds per campus planOFOI
ElectricalMV switchgear lineups (A/B)8EA34.5 kV, A/B lineups (~40 MW each)A/B (2N) MV distribution to blocksOFCI
ElectricalUnit substation transformers56EA3,750 kVA, 34.5 kV – 480 VOne per block; N + 1 per 6OFCI
ElectricalLV main switchboards (one per block)56EA480 V main switchboard per blockOne per blockOFCI
ElectricalNatural gas standby generators (3.25 MW class, lean-burn, enclosure)56EA3.25 MW class, natural gasOne per block; N + 1 per 6OFCI
ElectricalTransfer switches / paralleling56EAGenerator paralleling / transfer per blockOne per blockOFCI
ElectricalUPS systems (static, modular)142,875kWStatic modular; 1.25 × IT loadBlock-redundant; CDUs and pumps on UPSOFCI
ElectricalUPS batteries (Li-ion, 5-min)142,875kWLithium-ion, ~5 minutesNFPA 855 roomsOFCI
ElectricalFloor PDUs (500 kVA)229EA500 kVAA/B distributionOFCI
ElectricalOverhead busway, high-amp (incl. tap-offs)6,700LFHigh-amp, incl. tap-offsA/B over every lineupOFCI
ElectricalEPMS114.3MWMeters and head-endIntegrated with BMSCFCI
MechanicalAir-cooled chillers w/ free cooling (installed)87EA500 tons each, integral free cooling43,500 t provided vs 42,900 t requiredOFCI
MechanicalCoolant distribution units (2 MW)52EA2 MW eachN + 1 per 8OFCI
MechanicalHydronic pumps with VFDs58EAPrimary / process CHWDuty / standby pairsCFCI
MechanicalBuffer / thermal storage tanks4EABuffer volume for ride-throughSized with UPS ride-throughCFCI
MechanicalFan walls / CRAH for residual air22,860.0kWResidual air cooling20% of IT heat to airCFCI
MechanicalDOAS / makeup air6EAVentilation and humidity controlN + 1CFCI
MechanicalTCS stainless piping to lineups9,400LFStainless technology cooling loopSupply / return per lineupCFCI
MechanicalRack manifolds & quick-disconnects880EAOne per rackSplit per OFCI Matrix (often tenant)See OFCI
Fire / life safetyFire pumps & controllers2EAElectric, with controllersPer NFPA 20CFCI
Fire / life safetyDouble-interlock preaction (halls, electrical)348,000SFHalls and electrical roomsWith nitrogen generatorsCFCI
Fire / life safetyVESDA aspirating smoke detection348,000SFAspirating smoke detectionEarly warningCFCI
ConveyingHeavy freight elevators (10,000 lb)2EA10,000 lbIT and equipment movesCFCI
Controls / ITBMS / controls25,200PTBMS pointsRedundant servers / networkCFCI
Controls / ITMeet-me rooms / entrance facilities2EADiverse carrier entrancesTwo MMRsCFCI
SiteNatural gas service lateral & metering/regulating station1LSLateral + metering / regulating stationGas generators onlyOFOI
OFCI = owner furnished, contractor installed · CFCI = contractor furnished and installed · OFOI = owner furnished and installed. Procurement split follows the OFCI matrix (section 09). This schedule is a conceptual basis of design for pricing, not a design document.
© 2026 Frank Fernandez · Programmatic Builder developed for Capitol Construction Management · capitolcm.com  |  Sample report — concept program, not a real project · Concept estimate (AACE Class 4) · Not a quote06
Capitol/CMSample report · Programmatic Builder · Concept Data Center — Southside VACost summary
04 · Cost summary

$924.2M direct cost per building

2026-11-19T10:36:22.059037 image/svg+xml Matplotlib v3.11.2, https://matplotlib.org/ $0M $100M $200M $300M $400M $500M $600M All other (17 divisions) 07 Thermal & Moisture Protection 33 Utilities 03 Concrete 01 General Requirements 05 Metals 23 HVAC / Cooling 26 Electrical $60.4M · 6.5% $9.5M · 1.0% $12.1M · 1.3% $22.5M · 2.4% $25.5M · 2.8% $56.9M · 6.2% $164.8M · 17.8% $572.3M · 61.9%
DivDescriptionCost$/GSF$/IT MW% direct
01General Requirements$25,532,354$55.85$223K2.8%
02Existing Conditions$250,000$0.55$2K0.0%
03Concrete$22,520,967$49.26$197K2.4%
04Masonry$3,078,000$6.73$27K0.3%
05Metals$56,948,200$124.56$498K6.2%
06Wood, Plastics & Composites$632,880$1.38$6K0.1%
07Thermal & Moisture Protection$9,528,899$20.84$83K1.0%
08Openings$4,140,200$9.06$36K0.4%
09Finishes$4,790,440$10.48$42K0.5%
10Specialties$650,000$1.42$6K0.1%
11Equipment$228,000$0.50$2K0.0%
12Furnishings$150,000$0.33$1K0.0%
13Special Construction$998,640$2.18$9K0.1%
14Conveying Equipment$2,400,000$5.25$21K0.3%
21Fire Suppression$7,102,600$15.53$62K0.8%
22Plumbing$2,757,680$6.03$24K0.3%
23HVAC / Cooling$164,822,520$360.50$1,442K17.8%
25Integrated Automation$6,552,000$14.33$57K0.7%
26Electrical$572,302,491$1,251.76$5,007K61.9%
27Communications$8,268,640$18.09$72K0.9%
28Electronic Safety & Security$7,999,960$17.50$70K0.9%
31Earthwork$4,039,246$8.83$35K0.4%
32Exterior Improvements$6,389,911$13.98$56K0.7%
33Utilities$12,077,525$26.42$106K1.3%
Direct cost subtotal$924,161,153$2,021.35$8,085K100.0%
© 2026 Frank Fernandez · Programmatic Builder developed for Capitol Construction Management · capitolcm.com  |  Sample report — concept program, not a real project · Concept estimate (AACE Class 4) · Not a quote07
Capitol/CMSample report · Programmatic Builder · Concept Data Center — Southside VAIndirects
05 · Indirect stack & estimate confidence

$154.8M of indirects — 16.7% on direct

2026-11-19T10:36:22.118426 image/svg+xml Matplotlib v3.11.2, https://matplotlib.org/ $0M $10M $20M $30M $40M $50M Fee GC preconstruction fee GC payment & performance bond Other insurance by GC OCIP General Conditions Subcontractor default insurance (SDI) Construction contingency $40.9M · 4.43% $2.0M · 0.22% $8.2M · 0.89% $5.1M · 0.55% $15.1M · 1.64% $28.2M · 3.05% $9.0M · 0.97% $46.2M · 5.00%
IndirectAmount% of direct$/GSF
Direct cost subtotal$924,161,153100.00%$2,021.35
Construction contingency$46,208,0585.00%$101.07
Subcontractor default insurance (SDI)$8,986,2880.97%$19.66
General Conditions$28,228,5253.05%$61.74
OCIP$15,113,7601.64%$33.06
Other insurance by GC$5,113,4890.55%$11.18
GC payment & performance bond$8,222,4900.89%$17.98
GC preconstruction fee$2,000,0000.22%$4.37
Fee$40,923,3344.43%$89.51
Indirect cost subtotal$154,795,94416.75%$338.57
Grand total — one building$1,078,957,097$2,359.92

Estimate confidence

RatingMeaningDirect costShare
Highcommon unit ranges$36,237,4093.9%
Mediumneeds budget quote / takeoff$596,693,74464.6%
Lowallowance or scope-dependent$291,230,00031.5%
General Conditions are built bottom-up from a 78.5-FTE peak GC staffing plan (1,300 staff-months, burden ×1.62). Lines rated Medium or Low should be priced with budget quotes before the estimate is relied on for a funding decision.
© 2026 Frank Fernandez · Programmatic Builder developed for Capitol Construction Management · capitolcm.com  |  Sample report — concept program, not a real project · Concept estimate (AACE Class 4) · Not a quote08
Capitol/CMSample report · Programmatic Builder · Concept Data Center — Southside VAProgram total
06 · Program total & development cost

Total development cost $5.38B

Building 1 carries the full estimate. Buildings 2–4 repeat it with a site development factor of 0.80, are escalated at 4.0% per year to each construction midpoint, and carry owner soft costs and contingency.

2026-11-19T10:36:22.182400 image/svg+xml Matplotlib v3.11.2, https://matplotlib.org/ $0M $50M $100M $150M $200M $250M $300M Owner's development contingency Legal, insurance, financing & other owner costs Permits, fees, testing & inspections Commissioning agent Owner's program / construction management Design & engineering $256.3M $46.9M $46.9M $35.2M $70.4M $234.6M
LineRate / inputBasisAmount (escalated)
Construction — all buildings—From table above$4,691,261,252
Campus-wide infrastructure (substations, MV backbone, roads, water / sewer, on-site generation)—Enter from the Campus Conceptual Estimate or owner budget ($)$0
Design & engineering (A/E, MEP, structural, civil)5.00%% of construction$234,563,063
Owner's program / construction management1.50%% of construction$70,368,919
Commissioning agent (L1–L5)0.75%% of construction$35,184,459
Permits, fees, testing & inspections (owner-held)1.00%% of construction$46,912,613
Legal, insurance, financing & other owner costs1.00%% of construction$46,912,613
Land—Enter owner's land cost ($) — reference$0
Subtotal before owner contingency—$5,125,202,918
Owner's development contingency5.00%% of subtotal, excluding land — scope growth, tenant changes, market risk$256,260,146
Total project development costescalated, excl. IT equipment$5,381,463,064
Development $ / IT MW
$11.77M
Development $ / GSF
$2,943
Site-factor saving vs full repeat
$15.5M
Land and campus-wide infrastructure (substations, MV backbone, campus roads, on-site generation) are carried at $0 until the owner's figures are entered. Soft-cost and contingency rates are planning allowances.
© 2026 Frank Fernandez · Programmatic Builder developed for Capitol Construction Management · capitolcm.com  |  Sample report — concept program, not a real project · Concept estimate (AACE Class 4) · Not a quote09
Capitol/CMSample report · Programmatic Builder · Concept Data Center — Southside VACash flow
07 · Cash flow

Program spend peaks at $242M a month

Program — annual spend (escalated $)

2026-11-19T10:36:22.244488 image/svg+xml Matplotlib v3.11.2, https://matplotlib.org/ 2025 2026 2027 2028 2029 2030 $0M $500M $1.0B $1.5B $2.0B $2.5B $11.5M $69.4M $229.0M $1.99B $2.46B $619.6M Construction (all buildings) Development costs (owner)
YearConstructionDevelopmentTotalCumulative% of programBldg starts
2025$0.0M$11.5M$11.5M$11.5M0.2%0
2026$0.0M$69.4M$69.4M$81.0M1.3%0
2027$71.5M$157.6M$229.0M$310.0M4.3%1
2028$1,769.8M$217.2M$1,986.9M$2,297.0M36.9%2
2029$2,292.5M$172.4M$2,464.9M$4,761.8M45.8%1
2030$557.5M$62.1M$619.6M$5,381.5M11.5%0
Total$4,691.3M$690.2M$5,381.5M4

Building 1 — construction cash flow (Q4 2026 $, before retainage)

2026-11-19T10:36:22.360143 image/svg+xml Matplotlib v3.11.2, https://matplotlib.org/ Jul 2027 Jan 2028 Jul 2028 Jan 2029 $0M $20M $40M $60M $80M $100M $120M Peak $118.5M Jun 2028 Monthly spend Jul 2027 Jan 2028 Jul 2028 Jan 2029 0% 20% 40% 60% 80% 100% 50% by Jun 2028 Cumulative % complete (cost)
Peak program month March 2029 · peak year 2029 at $2,465M · Building 1 peak month $118.5M. Cash flow ties to the estimate (check = 0).
© 2026 Frank Fernandez · Programmatic Builder developed for Capitol Construction Management · capitolcm.com  |  Sample report — concept program, not a real project · Concept estimate (AACE Class 4) · Not a quote10
Capitol/CMSample report · Programmatic Builder · Concept Data Center — Southside VASchedule
08 · Schedule

NTP Jul 2027 · Building 1 RFS Feb 2029 · last RFS Aug 2030

Campus program

2026-11-19T10:36:22.492304 image/svg+xml Matplotlib v3.11.2, https://matplotlib.org/ 2027 2028 2029 2030 2031 2032 2033 2034 P-M1 Phase 1 complete (sample) B-04 Building 4 B-03 Building 3 B-02 Building 2 B-01 Building 1 C-07 On-site gas generation — stage 2 C-06 On-site gas generation — stage 1 C-M3 Permanent utility power available C-05 Utility substation (owner-funded portion) C-04 Campus MV backbone, roads, water / sewer, fiber C-03 Early grading & mass earthwork C-M2 Permits issued (site / building) C-02 Phase 1 design to IFC C-01 GC / CM selection (RFQ, RFP, award) C-M1 Owner lease / program approval Aug 31, 2030 Jan 29 – Aug 30 Jul 28 – Feb 30 Jan 28 – Aug 29 Jul 27 – Feb 29 Dec 30 – Jun 33 Dec 27 – Jun 30 Jul 31, 2028 Dec 26 – Jun 28 Dec 26 – Mar 28 Sep 26 – Jun 27 Apr 30, 2027 May 26 – May 27 Jul 26 – Nov 26 Apr 30, 2026 Status date

Building 1 — key activities & milestones

2026-11-19T10:36:22.609205 image/svg+xml Matplotlib v3.11.2, https://matplotlib.org/ 2027 2028 2029 2030 9.10 Tenant rack-in (OFOI) 9.08 Substantial completion / Ready for Service 9.07 L5 — integrated systems test (IST) 9.06 L4 — functional performance tests 9.02 L2 — installation verification 6.05 TCS piping to lineups 6.01 Chillers — set & connect 5.04 Natural gas generators — set & connect 4.01 ROS — natural gas generators 3.10 Building dry-in 3.04 Structural steel framing 2.13 First gas available (utility) 1.03 GC / CM award (Notice of Award) 1.01 Design development → IFC (Building 1) Feb 29 – Apr 29 Feb 28, 2029 Jan 29 – Feb 29 Nov 28 – Jan 29 Jun 28 – Nov 28 Jun 28 – Nov 28 Feb 28 – Aug 28 Feb 28 – Oct 28 Jan 04, 2028 Jul 31, 2028 Oct 27 – May 28 Dec 24, 2027 Dec 31, 2026 May 26 – May 27 Status date
BuildingElectricalProcurement / CxStructureEnabling / generationMilestone
© 2026 Frank Fernandez · Programmatic Builder developed for Capitol Construction Management · capitolcm.com  |  Sample report — concept program, not a real project · Concept estimate (AACE Class 4) · Not a quote11
Capitol/CMSample report · Programmatic Builder · Concept Data Center — Southside VALong-lead
09 · Long-lead & OFCI procurement

4 items past their order-by date, 3 to order now

Order-by dates are back-scheduled from each item's Building 1 install start (install − ROS buffer − transit − lead time − submittals − bid / award). Status date Nov 13, 2026.

IDSystem / equipmentTypeQtyLead (wks)PO / order byRequired on siteFlag
U-01Utility substation & revenue metering (campus feed)OFOI1 LS104Oct 08, 2025Oct 06, 2027PAST — confirm slot
E-03Unit substation transformers 3,750 kVA (56)OFCI5680Mar 31, 2026Jan 04, 2028PAST — confirm slot
E-01Natural gas generators 3.25 MW, enclosed (56)OFCI5680Apr 07, 2026Jan 04, 2028PAST — confirm slot
E-02MV switchgear 34.5 kV (main / ring)OFCI670Jul 15, 2026Feb 02, 2028PAST — confirm slot
U-02Natural gas service & meter setOFOI1 LS40Nov 13, 2026Aug 20, 2027Order now
M-01Air-cooled chillers 500 t (87)OFCI8744Dec 29, 2026Jan 04, 2028Order now
E-04LV switchboards / paralleling gearOFCI5645Jan 13, 2027Feb 02, 2028Order now
E-10MV cable 35 kV & terminationsCFCILS30Apr 27, 2027Jan 18, 2028OK
E-05UPS modules (static, modular)OFCI5636May 01, 2027Mar 04, 2028OK
M-02CDUs 2 MW (liquid cooling)OFCI5232Jun 12, 2027Mar 18, 2028OK
S-03Elevators (freight)CFCI240Jun 17, 2027May 18, 2028OK
E-06Li-ion battery cabinetsOFCI5630Aug 19, 2027May 18, 2028OK
E-08Overhead busway, high-ampOFCI6,700 LF26Aug 23, 2027Apr 17, 2028OK
E-07PDUs / RPPsOFCI11224Sep 06, 2027Apr 17, 2028OK
L-05Access control & CCTV head-endOFOILS16Feb 22, 2028Jul 18, 2028OK
I-02Meet-me room carrier equipmentOFOILS20Apr 23, 2028Sep 17, 2028OK
M-04Rack manifolds, hoses, quick disconnectsOFOI88020May 19, 2028Nov 17, 2028OK
I-01Server racks & IT equipmentOFOI88030Jun 08, 2028Jan 18, 2029OK
E-09Busway tap-off boxes to racksOFOI88016Jun 16, 2028Nov 17, 2028OK
PAST — confirm slot means the back-scheduled order-by is earlier than the status date: confirm a manufacturing slot exists under the owner's supply agreements, or the install date moves. Lead times are planning assumptions — confirm with vendors.
© 2026 Frank Fernandez · Programmatic Builder developed for Capitol Construction Management · capitolcm.com  |  Sample report — concept program, not a real project · Concept estimate (AACE Class 4) · Not a quote12
Capitol/CMSample report · Programmatic Builder · Concept Data Center — Southside VAStaffing & KPIs
10 · Staffing & owner's-rep KPIs

Peak program staff 293 — 250 GC, 43 owner

2026-11-19T10:36:22.708408 image/svg+xml Matplotlib v3.11.2, https://matplotlib.org/ 2026 2027 2028 2029 2030 2031 0 50 100 150 200 250 300 350 Staff (people) Peak 293 (Feb 2029) GC staff on payroll Owner staff Total program staff

GC staffing KPIs — Building 1 (peak craft 1,600, safety 1:125)

KPIValueTypical rangeStatus
1. GC staffing as % of direct cost3.1%2% – 4%In range
2. General Conditions + General Requirements as % of direct cost5.8%5% – 9%In range
3. Craft per GC staff at peak20.415 – 25 : 1In range
4. Craft per superintendent at peak (excl. assistant supers)114.375 – 125 : 1In range
5. Craft per safety staff at peak123.150 – 100 : 1 (hyperscale owners often 1:50)Thin
6. Field share of staff at peak (field, safety, QA/QC, Cx)66.2%60% – 70%In range
7. GC staffing cost per IT MW$246,969Compare across buildings / bids—
8. Put-in-place per GC staff, peak month$1,509,276$1.0M – $2.0M / monthIn range
9. Staff to Volume (S/V) — fully burdened staff cost ÷ grand total2.6%2.0% – 4.0%In range
10. Return on Staff (ROS) — fee ÷ fully burdened staff cost1.45x1.0x – 2.0xIn range
11. Earnings to Volume (E/V) — fee ÷ grand total3.8%2.5% – 4.0%In range

Safety staffing scenarios (Building 1)

Safety ratioSafety staffAdded vs 1:125Added costGC total
1 : 125130$0$28,228,525
1 : 100163$899,100$29,127,625
1 : 75229$2,697,300$30,925,825
1 : 503219$5,694,300$33,922,825
Typical ranges are rules of thumb for $500M+ mission-critical GC work, not a published survey. S/V = fully burdened staff cost ÷ grand total; ROS = fee ÷ staff cost; E/V = fee ÷ grand total.
© 2026 Frank Fernandez · Programmatic Builder developed for Capitol Construction Management · capitolcm.com  |  Sample report — concept program, not a real project · Concept estimate (AACE Class 4) · Not a quote13
Capitol/CMSample report · Programmatic Builder · Concept Data Center — Southside VARegional
11 · Regional cost comparison

The same building in 13 markets

Building 1 re-priced line by line with market labor, material and seismic adjustments — same design, quantities and schedule. Order-of-magnitude reference only; location factors are planning assumptions, not quotes.

2026-11-19T10:36:22.793710 image/svg+xml Matplotlib v3.11.2, https://matplotlib.org/ $0M $2M $4M $6M $8M $10M $12M $14M $16M Grand total per IT MW (Q4 2026 $, one building) Southside VA (project) Atlanta, GA Dallas–Fort Worth, TX Dallas, TX (city / Dallas–Plano–Irving) Phoenix, AZ Columbus, OH Las Vegas / Reno, NV Salt Lake City, UT New York / NJ Northern Virginia (Ashburn) Portland / Hillsboro, OR Chicago, IL Silicon Valley (San Jose), CA $9.44M / MW · ×1.000 $9.58M / MW · ×1.015 $9.66M / MW · ×1.023 $9.77M / MW · ×1.035 $9.89M / MW · ×1.047 $9.91M / MW · ×1.049 $10.14M / MW · ×1.074 $10.34M / MW · ×1.095 $10.99M / MW · ×1.164 $11.01M / MW · ×1.166 $11.63M / MW · ×1.232 $11.79M / MW · ×1.249 $12.34M / MW · ×1.308
MarketElectrician $/hrLocation factor$/GSFPer buildingPer IT MWRank
Southside VA (base)$26.351.000$2,360$1,079M$9.44M1
Atlanta, GA$27.751.015$2,394$1,095M$9.58M2
Dallas–Fort Worth, TX$28.561.023$2,414$1,104M$9.66M3
Dallas, TX (city / Dallas–Plano–Irving)$29.711.035$2,442$1,117M$9.77M4
Phoenix, AZ$30.221.047$2,471$1,130M$9.89M5
Columbus, OH$31.111.049$2,476$1,132M$9.91M6
Las Vegas / Reno, NV$30.451.074$2,534$1,159M$10.14M7
Salt Lake City, UT$30.821.095$2,585$1,182M$10.34M8
New York / NJ$38.751.164$2,747$1,256M$10.99M9
Northern Virginia (Ashburn)$41.681.166$2,751$1,258M$11.01M10
Portland / Hillsboro, OR$42.851.232$2,907$1,329M$11.63M11
Chicago, IL$49.001.249$2,947$1,347M$11.79M12
Silicon Valley (San Jose), CA$48.551.308$3,086$1,411M$12.34M13
Location factor applies to direct cost; indirects held at the project ratio. Excludes sales / use tax, prevailing wage, union work rules and market-heat premiums beyond wages. Q4 2026 $, no escalation.
© 2026 Frank Fernandez · Programmatic Builder developed for Capitol Construction Management · capitolcm.com  |  Sample report — concept program, not a real project · Concept estimate (AACE Class 4) · Not a quote14
Capitol/CMSample report · Programmatic Builder · Concept Data Center — Southside VAMarket context
Market context — US Data Center Atlas

Southern Virginia: 7 campuses, 5,400 MW tracked

Comparables for this 457 MW program: Google Botetourt County (300 (est.) MW, under construction); Microsoft Boydton Campus (Azure East US) (1,100 MW, operational).

Campuses in the Southern Virginia market

CampusOperatorCityStatusMWNotes
STACK Southern Virginia Megasite (Berry Hill)STACK InfrastructureBerry Hill (Pittsylvania Co., near Danville)Planned3,000$100B / 30 yrs; 21 bldgs on ~1,733 ac; 2 on-site gas plants; early grading of ~400 ac approved Oct 2026; construction Q3 2027; 299 MW min load by …
Microsoft Boydton Campus (Azure East US)MicrosoftBoydtonOperational1,100$2B+ since 2010; expanded repeatedly
Microsoft Panhandle Road ExpansionMicrosoftBoydtonPlanned300 (est.)490 ac, 3 bldgs; filed Jun 2026
Microsoft AVC17 LakesideMicrosoftClarksvillePlanned300 (est.)259 ac, 3 bldgs; permits filed 2022
Google Botetourt CountyGoogleDalevilleUnder construction300 (est.)Grading started 2026; air-cooled design
Microsoft Tunstall RoadMicrosoftSouth HillPlanned200 (est.)132 ac greenfield, 3 bldgs; permits filed 2022
Ringgold Campus (Route 58 East)Anchorstone AdvisorsRinggold (Pittsylvania Co.)Planned200946 ac; rezoning approved unanimously Jul 2026

General contractors — Southern Virginia first, then rest of VA

GCCampusMarketRoleConfidence
No GCs recorded in Southern Virginia — nearest VA markets below.
DPR ConstructionDigital Realty Digital Loudoun PlazaNorthern VirginiaGC (Loudoun Exchange campus bldgs A,B,D,F,G,K)confirmed
HITT ContractingDigital Realty Manassas CampusNorthern VirginiaGC (Brickyard first building, 36 MW)confirmed
DPR ConstructionQTS Ashburn 1 & 2Northern VirginiaConstruction manager (Ashburn-Shellhorn)confirmed
HITT ContractingAligned IAD-01 AshburnNorthern VirginiaGC (named for IAD-02 on same Ashburn campus)confirmed
Clark ConstructionNTT VA1–VA7 AshburnNorthern VirginiaGC (VA6 and later Ashburn buildings)confirmed
DPR ConstructionMeta Henrico Data CenterRichmondGC / builder (DPR project page)confirmed

Contested-site flags — Southern Virginia and VA

No contest entries for Southern Virginia or VA in this Atlas copy.

Developer portfolio signals (Beale, Related Digital, 5C) — VA

No Beale, Related Digital or 5C campuses recorded in VA.

Atlas compiled October 18, 2026, updated November 16. Compiled from public reporting — status, MW (est. = estimated) and GC roles can lag or be wrong; nothing here is verified or owner data. Source: capitolcm.com/atlas.
© 2026 Frank Fernandez · Programmatic Builder developed for Capitol Construction Management · capitolcm.com  |  Sample report — concept program, not a real project · Concept estimate (AACE Class 4) · Not a quote15
Capitol/CMSample report · Programmatic Builder · Concept Data Center — Southside VARisks
12 · Risks & assumptions

7 schedule conflicts and 8 assumptions to confirm

Building 1 coordination checks — delivery vs readiness

CheckResult
Generators ROS vs equipment padsCONFLICT — 12 wks early
Transformers ROS vs equipment padsCONFLICT — 12 wks early
Chillers ROS vs equipment padsCONFLICT — 12 wks early
MV switchgear ROS vs dry-inCONFLICT — 26 wks early
LV switchboards ROS vs dry-inCONFLICT — 26 wks early
UPS ROS vs dry-inCONFLICT — 21 wks early
CDUs ROS vs dry-inCONFLICT — 19 wks early
Generator start-up (set finish) vs first gasOK
L4 start vs permanent utility powerOK
CONFLICT = equipment arrives before its pad or dry-in is ready: resequence, store off site, or move the install month.

Assumptions to confirm

Owner / tenant design standardRedundancy (block-redundant, N+1 per 6), 130 kW racks, 80% liquid cooling and PUE 1.25 are template defaults.
Standby fuelNatural gas generation — confirm service firmness, pressure and AHJ acceptance for standby use.
Campus infrastructure & landCarried at $0 — enter the owner's substation, MV backbone, on-site generation and land figures.
Escalation4.0% / yr from the Q4 2026 pricing date to each building midpoint.
Repetition & site factorsSite development factor 0.80; repetition factor 1.00; full GC team per building.
Owner procurementOFCI equipment lead times and ROS dates assume owner supply agreements — confirm manufacturing slots for items flagged PAST.
Utility powerPermanent power and first gas dates are schedule inputs; utility energization gates Level 4 / 5 commissioning.
Labor marketPeak craft of 1,600 and 40% imported staff — validate against competing regional work.
© 2026 Frank Fernandez · Programmatic Builder developed for Capitol Construction Management · capitolcm.com  |  Sample report — concept program, not a real project · Concept estimate (AACE Class 4) · Not a quote16
Capitol/CMSample report · Programmatic Builder · Concept Data Center — Southside VABasis
13 · Basis of estimate

Basis, exclusions and limitations

Classification

This is a conceptual, planning-level estimate consistent with AACE International Class 4 (feasibility / concept screening), with an expected accuracy range of roughly −20% / +30% around the point estimate. Building 1 is priced in Q4 2026 dollars; program totals are escalated to each building's construction midpoint.

Method

  • Quantities are derived from the concept massing (footprint, levels, equipment counts) and priced by CSI MasterFormat division with installed unit costs, each carrying a basis note and a confidence rating.
  • General Conditions are built from a position-by-position GC staffing plan; General Requirements, contingency, insurance, bond and fee are carried as itemized indirects.
  • Cash flow is cost-loaded by line item and sequence of operations; procurement dates are back-scheduled from installation needs.
  • Unit prices are planning-level ranges cross-checked against published industry benchmarks and labor wage data. They are not vendor quotes, subcontractor bids or licensed cost-database prices.

Exclusions

Land; campus-wide infrastructure (mass grading, campus roads, substations, campus MV, on-site gas generation / central power plant); tenant IT (servers, racks, network cabling to racks); financing; Virginia sales & use tax (owner equipment may qualify for the VA data center exemption — confirm eligibility); prevailing-wage requirements; hazardous materials; rock excavation beyond the ground improvement allowance. Escalation and owner soft costs are carried only in the program total (section 06).

Limitations

Unit prices, lead times and location factors in this report are planning assumptions — not quotes, owner data or commitments. Confirm design criteria with the owner, the tenant design standard, the design team and the authority having jurisdiction before relying on these figures for a funding or contracting decision.

Prepared by

Frank Fernandez · Owner's Representation · Mission Critical
Capitol Construction Management · capitolcm.com

Programmatic Builder is proprietary to Frank Fernandez, developed for Capitol Construction Management. © 2026 Frank Fernandez. Sample report — illustrates a concept program; not a real project.

© 2026 Frank Fernandez · Programmatic Builder developed for Capitol Construction Management · capitolcm.com  |  Sample report — concept program, not a real project · Concept estimate (AACE Class 4) · Not a quote17

Sample report — concept program, not a real project · Concept estimate (AACE Class 4) · Not a quote · © 2026 Frank Fernandez · Capitol Construction Management · capitolcm.com