Capitol/CM Sample report · Developer Program Report — 21 × 114 MW (2.4 GW) All sample reports View only
Capitol/CMSample report
Developer Program Report · AACE Class 4

Concept Hyperscale Program — 21 × 114 MW (2.4 GW)

21 × 114.3 MW IT buildings · 2,400.3 MW program · Southside VA · natural gas standby
2026-11-19T10:36:27.756441 image/svg+xml Matplotlib v3.11.2, https://matplotlib.org/ 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040
Total development cost
$34.21B
escalated · excl. IT equipment
Development $ / IT MW
$14.25M
all-in, escalated
Building 1
$1,076M
$9.42M / MW · $2,354 / GSF
Program
12.8 yrs
Jul 2027 – Mar 2040 · 3 phases
Prepared by Frank Fernandez · Capitol Construction ManagementPricing basis Nov 2026 $ · Report date Nov 19, 2026
Capitol/CMSample report · Developer Program Planner · Concept Hyperscale Program — 21 × 114 MW (2.4 GW)Summary
Executive summary

$34.21B to deliver 2,400.3 MW over 12.8 years

21 buildings of 114.3 MW IT in Southside VA, 7 per phase on a 6-month cadence with phases 48 months apart. Building 1 NTP July 2027; last building ready for service March 2040.

Total development cost
$34.21B
2,400.3 IT MW · 21 bldgs
Building 1 construction
$1,076M
$9.42M / MW · $2,354 / GSF
Development $ / IT MW
$14.25M
escalated, all-in
Yield on cost
9.43%
placeholder underwriting inputs
Program duration
12.8 yrs
Jul 2027 – Mar 2040
Delivery pace
188 MW/yr
peak qtr $995.3M
Peak program craft
3,733
1,600 per building
Peak owner team
26 FTE
GC field staff peak 173

What to watch

  • Safety coverage: 1 safety professional per 123 craft at 125:1 target; moving to 1:50 adds 19 FTE, about $5.0M per building.
  • Long-lead procurement: 4 Building 1 items past the order-by date and 3 to order within 3 months of Nov 19, 2026.
  • Peak demand: 3,733 craft and 26 owner FTE at peak; peak quarter spend $995.3M.
  • Escalation: 4%/yr from the Nov 2026 basis to each building midpoint adds $7.36B to construction.

Program inputs

InputValueInputValue
IT load per building114.3 MWMarketSouthside VA
Buildings / per phase21 / 7Building 1 NTPJul 2027
Cadence / phase offset6 / 48 moConstruction duration20 mo
Levels / rack density2 / 130 kWEscalation4% / yr
Generator fuelNatural gasSite / repetition / GC factors, bldgs 2+0.80 / 1.00 / 1.00
Fee / contingency3.95% / 5%Campus infrastructure / land$0 / $0
© 2026 Frank Fernandez · Developer Program Planner developed for Capitol Construction Management · capitolcm.com  |  Sample report — concept program, not a real project · Concept estimate (AACE Class 4) · Not a quote02
Capitol/CMSample report · Developer Program Planner · Concept Hyperscale Program — 21 × 114 MW (2.4 GW)Development cost
01 · Development cost

Total development cost $34.21B

Construction is 87% of the total. Building 1 carries the full estimate; buildings 2+ apply the site, repetition and GC factors and are escalated to each construction midpoint.

2026-11-19T10:36:27.829874 image/svg+xml Matplotlib v3.11.2, https://matplotlib.org/ $0M $250M $500M $750M $1.0B $1.2B $1.5B $1.8B $2.0B Owner contingency Legal & financing Permits & fees Commissioning agent Owner's program management Design / A&E $1.63B $298.2M $298.2M $223.7M $447.3M $1.49B
LineBasisAmount% of TDC
Construction — all buildings (escalated)21 buildings$29,821,016,23587.2%
Design / A&E5% of construction$1,491,050,8124.4%
Owner's program management1.5% of construction$447,315,2441.3%
Commissioning agent0.75% of construction$223,657,6220.7%
Permits & fees1% of construction$298,210,1620.9%
Legal & financing1% of construction$298,210,1620.9%
Campus infrastructureinput$00.0%
Landinput$00.0%
Owner contingency5% excl. land$1,628,973,0124.8%
Total development costescalated, excl. IT equipment$34,208,433,249100.0%
Construction $ / IT MW
$12.42M
Development $ / IT MW
$14.25M
Escalation in construction
$7.36B
Campus infrastructure and land are inputs ($0 and $0 in this scenario). Soft-cost and contingency rates are planning allowances; replace with the owner's budget structure when available.
© 2026 Frank Fernandez · Developer Program Planner developed for Capitol Construction Management · capitolcm.com  |  Sample report — concept program, not a real project · Concept estimate (AACE Class 4) · Not a quote03
Capitol/CMSample report · Developer Program Planner · Concept Hyperscale Program — 21 × 114 MW (2.4 GW)Schedule
02 · Program schedule

21 buildings in 3 phases, Jul 2027 – Mar 2040

2026-11-19T10:36:27.935636 image/svg+xml Matplotlib v3.11.2, https://matplotlib.org/ 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 B21 B20 B19 B18 B17 B16 B15 B14 B13 B12 B11 B10 B9 B8 B7 B6 B5 B4 B3 B2 B1
Phase 1Phase 2Phase 3
BldgPhaseStartRFSNov 2026 $EscalationEscalated
B11Jul 2027Mar 2029$1,076.4M1.061$1,141.6M
B21Jan 2028Sep 2029$1,069.2M1.082$1,156.5M
B31Jul 2028Mar 2030$1,069.2M1.103$1,179.4M
B41Jan 2029Sep 2030$1,069.2M1.125$1,202.7M
B51Jul 2029Mar 2031$1,069.2M1.147$1,226.6M
B61Jan 2030Sep 2031$1,069.2M1.170$1,250.8M
B71Jul 2030Mar 2032$1,069.2M1.193$1,275.6M
B82Jul 2031Mar 2033$1,069.2M1.241$1,326.6M
B92Jan 2032Sep 2033$1,069.2M1.265$1,352.9M
B102Jul 2032Mar 2034$1,069.2M1.290$1,379.7M
B112Jan 2033Sep 2034$1,069.2M1.316$1,407.0M
B122Jul 2033Mar 2035$1,069.2M1.342$1,434.9M
B132Jan 2034Sep 2035$1,069.2M1.369$1,463.3M
B142Jul 2034Mar 2036$1,069.2M1.396$1,492.3M
B153Jul 2035Mar 2037$1,069.2M1.451$1,552.0M
B163Jan 2036Sep 2037$1,069.2M1.480$1,582.7M
B173Jul 2036Mar 2038$1,069.2M1.510$1,614.1M
B183Jan 2037Sep 2038$1,069.2M1.539$1,646.0M
B193Jul 2037Mar 2039$1,069.2M1.570$1,678.6M
B203Jan 2038Sep 2039$1,069.2M1.601$1,711.9M
B213Jul 2038Mar 2040$1,069.2M1.633$1,745.8M
Total$22,460.9M$29,821.0M
© 2026 Frank Fernandez · Developer Program Planner developed for Capitol Construction Management · capitolcm.com  |  Sample report — concept program, not a real project · Concept estimate (AACE Class 4) · Not a quote04
Capitol/CMSample report · Developer Program Planner · Concept Hyperscale Program — 21 × 114 MW (2.4 GW)Building 1
03 · Building 1

Building 1: $1,076.4M · $9.42M per MW

114.3 MW IT, 457,200 GSF on 2 levels, 880 racks at 130 kW, 56 × 3 MW blocks with natural gas generators and 87 chillers. Priced in Southside VA with the Programmatic Builder engine.

2026-11-19T10:36:28.016007 image/svg+xml Matplotlib v3.11.2, https://matplotlib.org/ $0M $100M $200M $300M $400M $500M $600M $700M Communications Interiors & specialties Fire protection & security Site development & utilities Structure & envelope Mechanical & cooling Electrical & generation $8.3M · 0.9% $9.2M · 1.0% $15.1M · 1.6% $22.8M · 2.5% $96.8M · 10.5% $178.1M · 19.3% $568.4M · 61.5%
Cost groupCSIAmount% of total
Site development & utilities02 · 31–33$22,756,6822.1%
Structure & envelope03–08$96,849,1469.0%
Interiors & specialties09–14$9,217,0800.9%
Electrical & generation26$568,382,49152.8%
Mechanical & cooling22 · 23 · 25$178,052,20016.5%
Fire protection & security21 · 28$15,102,5601.4%
Communications27$8,268,6400.8%
Trade directs$898,628,79983.5%
General Requirements$25,762,9952.4%
General Conditions$25,584,3202.4%
Contingency$46,219,5904.3%
SDI$8,986,2880.8%
OCIP$15,077,7301.4%
Other insurance$5,101,2990.5%
P&P bond$8,202,8880.8%
Preconstruction fee$2,000,0000.2%
Fee$40,825,7743.8%
Building 1 total$1,076,389,683100.0%

Owner's-rep KPIs (Planner definitions)

KPIValueDefinition
S/V2.38%General Conditions ÷ construction volume
ROS3.79%Fee ÷ volume
E/V52.8%Major electrical and cooling equipment ÷ volume
Safety ratio1 : 123Peak craft ÷ safety professionals
Craft per GC staff / per superintendent28.1 / 100Peak craft ÷ GC staff; ÷ superintendents
© 2026 Frank Fernandez · Developer Program Planner developed for Capitol Construction Management · capitolcm.com  |  Sample report — concept program, not a real project · Concept estimate (AACE Class 4) · Not a quote05
Capitol/CMSample report · Developer Program Planner · Concept Hyperscale Program — 21 × 114 MW (2.4 GW)Cash flow
04 · Cash flow

Spend peaks at $995.3M a quarter; 2038 is the peak year

Program spend by quarter (escalated $, all-in)

2026-11-19T10:36:28.126825 image/svg+xml Matplotlib v3.11.2, https://matplotlib.org/ 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 $0M $200M $400M $600M $800M $1.0B Peak quarter $995.3M Oct 2038

Annual spend

YearSpendCumulative% of TDCStarts
2027$324.8M$324.8M0.9%1
2028$2,248.7M$2,573.5M6.6%2
2029$2,730.2M$5,303.7M8.0%2
2030$2,839.3M$8,143.0M8.3%2
2031$1,888.8M$10,031.8M5.5%1
2032$2,642.7M$12,674.6M7.7%2
2033$3,193.8M$15,868.4M9.3%2
2034$3,321.6M$19,189.9M9.7%2
2035$2,209.6M$21,399.6M6.5%1
2036$3,091.6M$24,491.2M9.0%2
2037$3,736.3M$28,227.5M10.9%2
2038$3,885.8M$32,113.2M11.4%2
2039$2,068.4M$34,181.6M6.0%0
2040$26.8M$34,208.4M0.1%0
Total$34,208.4M100.0%21
2026-11-19T10:36:28.214827 image/svg+xml Matplotlib v3.11.2, https://matplotlib.org/ 2028 2030 2032 2034 2036 2038 2040 0% 20% 40% 60% 80% 100% 50% by May 2034 Cumulative spend
Peak month $338.2M. Cash flow ties to total development cost (difference -0). Soft costs and owner contingency follow construction spend; land at month 1; campus infrastructure over the first 18 months.
© 2026 Frank Fernandez · Developer Program Planner developed for Capitol Construction Management · capitolcm.com  |  Sample report — concept program, not a real project · Concept estimate (AACE Class 4) · Not a quote06
Capitol/CMSample report · Developer Program Planner · Concept Hyperscale Program — 21 × 114 MW (2.4 GW)Staffing
05 · Staffing

Peak 3,733 craft, 173 GC field staff, 26 owner FTE

Program craft headcount

2026-11-19T10:36:28.283826 image/svg+xml Matplotlib v3.11.2, https://matplotlib.org/ 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 0 1000 2000 3000 4000 Craft (people) 3,733

GC staff and owner team

2026-11-19T10:36:28.359636 image/svg+xml Matplotlib v3.11.2, https://matplotlib.org/ 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 0 50 100 150 200 Staff (FTE) 173 26 GC field staff Owner team

GC roster — Building 1 (57 FTE, $25,584,320)

RoleQtyBaseCost
General Superintendent1$350K$1,160,625
Project Executive1$300K$994,821
Senior Project Manager1$225K$746,116
Project Manager2$185K$1,226,946
Assistant Project Manager3$135K$1,275,858
Area Superintendent8$200K$4,775,143
Assistant Superintendent5$150K$2,113,996
MEP Superintendent2$190K$1,071,091
MEP Coordinator3$170K$1,352,957
Project Engineer6$110K$2,079,177
Safety Manager1$160K$530,571
Safety Specialist12$105K$3,551,512
QA/QC Manager2$160K$955,029
Scheduler1$165K$547,152
Cost Engineer2$150K$994,821
Commissioning Coordinator2$165K$547,152
BIM / VDC Manager1$140K$371,400
Logistics Manager1$140K$394,612
Procurement Manager1$150K$397,929
Project Administrator2$75K$497,411

Owner team

Program roles (fixed)
Program Executive
Development Director
Program Controls Lead
Procurement / OFCI Lead
Utility & Power Lead
Entitlements & Permitting Lead
EHS Lead
Finance & Draw Manager
Per active buildingFTE
Owner's Project Manager1
Owner's Construction Manager1
Owner's MEP Engineer0.5
Commissioning Manager0.5
Cost & Schedule Controls0.5
Owner QA/QC0.5
Plus one buyer per 3 active buildings. Owner team cost over the program $66.6M at $260K loaded per FTE-year (assumption).
© 2026 Frank Fernandez · Developer Program Planner developed for Capitol Construction Management · capitolcm.com  |  Sample report — concept program, not a real project · Concept estimate (AACE Class 4) · Not a quote07
Capitol/CMSample report · Developer Program Planner · Concept Hyperscale Program — 21 × 114 MW (2.4 GW)Long-lead
06 · Long-lead & OFCI procurement

4 past order-by, 3 to order within 3 months — Building 1

Order-by = install month − (on-site buffer + transit + lead time + submittals), from Building 1 NTP Jul 2027. Status date Nov 19, 2026. Later buildings repeat on their own start dates; owner supply agreements should cover the full program quantity.

IDItemTypeQtyLead (wks)Order byInstallStatus
U-01Utility substation & meteringOFOIlot104Oct 2025Dec 2027Past order-by
E-03Unit substation transformers 3,750 kVAOFCI5680Mar 2026Feb 2028Past order-by
E-01GeneratorsOFCI5680Apr 2026Feb 2028Past order-by
E-02MV switchgear 34.5 kVOFCIlot70Jul 2026Mar 2028Past order-by
U-02Natural gas service & meter setOFOIlot40Nov 2026Oct 2027Order within 3 mo
M-01Air-cooled chillers 500 tOFCI8744Dec 2026Feb 2028Order within 3 mo
E-04LV switchboards / paralleling gearOFCIlot45Jan 2027Mar 2028Order within 3 mo
S-01Structural steelCFCIlot16Feb 2027Sep 2027Order before NTP
E-05UPS modulesOFCIlot36Apr 2027Apr 2028Order before NTP
M-02CDUs (liquid cooling)OFCI5232Jun 2027Apr 2028Order before NTP
S-03Freight elevatorsCFCIlot40Jun 2027Jun 2028Order before NTP

Program exposure — buildings already inside each item's lead time

EquipmentBldgs past order-byFirst on-time buildingIts order-by
Utility substation & metering3 bldgsB4Apr 2027
Unit substation transformers 3,750 kVA2 bldgsB3Mar 2027
Generators2 bldgsB3Apr 2027
MV switchgear 34.5 kV1 bldgsB2Jan 2027
Natural gas service & meter set0B1Nov 2026
Air-cooled chillers 500 t0B1Dec 2026
LV switchboards / paralleling gear0B1Jan 2027
Structural steel0B1Feb 2027
UPS modules0B1Apr 2027
CDUs (liquid cooling)0B1Jun 2027
Freight elevators0B1Jun 2027

Program quantities: 1,176 generators · 1,176 unit substations · 1,827 chillers · 1,092 CDUs.

Lead times are planning assumptions — confirm with vendors and the owner's master supply agreements. Options for late items: reserve manufacturing slots or framework agreements now, move NTP, or resequence so later buildings take the first deliveries.
© 2026 Frank Fernandez · Developer Program Planner developed for Capitol Construction Management · capitolcm.com  |  Sample report — concept program, not a real project · Concept estimate (AACE Class 4) · Not a quote08
Capitol/CMSample report · Developer Program Planner · Concept Hyperscale Program — 21 × 114 MW (2.4 GW)Markets
07 · Market comparison

The same program in 14 markets

Every market re-priced with the same inputs — only labor, material and seismic factors change. Order-of-magnitude reference; location factors are planning assumptions, not quotes.

2026-11-19T10:36:28.460218 image/svg+xml Matplotlib v3.11.2, https://matplotlib.org/ $0M $5M $10M $15M $20M $25M Total development cost per IT MW (escalated, same program) Southside VA (selected) Atlanta, GA Dallas–Fort Worth, TX Dallas, TX (city / Dallas–Plano–Irving) Tucson, AZ (Pima County) Phoenix, AZ Columbus, OH Las Vegas / Reno, NV Salt Lake City, UT New York / NJ Northern Virginia (Ashburn) Portland / Hillsboro, OR Chicago, IL Silicon Valley (San Jose), CA $14.25M / MW · TDC $34.21B $14.46M / MW · TDC $34.71B $14.58M / MW · TDC $35.00B $14.75M / MW · TDC $35.41B $14.80M / MW · TDC $35.53B $14.93M / MW · TDC $35.83B $14.96M / MW · TDC $35.91B $15.30M / MW · TDC $36.72B $15.59M / MW · TDC $37.43B $16.59M / MW · TDC $39.83B $16.64M / MW · TDC $39.93B $17.55M / MW · TDC $42.13B $17.83M / MW · TDC $42.79B $18.64M / MW · TDC $44.73B
MarketElectrician $/hrBuilding 1B1 $/MWTDCTDC $/MW
Southside VA$26.35$1,076M$9.42M$34.21B$14.25M
Atlanta, GA$27.75$1,092M$9.56M$34.71B$14.46M
Dallas–Fort Worth, TX$28.56$1,101M$9.64M$35.00B$14.58M
Dallas, TX (city / Dallas–Plano–Irving)$29.71$1,114M$9.75M$35.41B$14.75M
Tucson, AZ (Pima County)$29.37$1,118M$9.78M$35.53B$14.80M
Phoenix, AZ$30.22$1,127M$9.86M$35.83B$14.93M
Columbus, OH$31.11$1,130M$9.89M$35.91B$14.96M
Las Vegas / Reno, NV$30.45$1,156M$10.11M$36.72B$15.30M
Salt Lake City, UT$30.82$1,178M$10.31M$37.43B$15.59M
New York / NJ$38.75$1,253M$10.96M$39.83B$16.59M
Northern Virginia (Ashburn)$41.68$1,256M$10.99M$39.93B$16.64M
Portland / Hillsboro, OR$42.85$1,326M$11.60M$42.13B$17.55M
Chicago, IL$49.00$1,346M$11.78M$42.79B$17.83M
Silicon Valley (San Jose), CA$48.55$1,408M$12.31M$44.73B$18.64M
© 2026 Frank Fernandez · Developer Program Planner developed for Capitol Construction Management · capitolcm.com  |  Sample report — concept program, not a real project · Concept estimate (AACE Class 4) · Not a quote09
Capitol/CMSample report · Developer Program Planner · Concept Hyperscale Program — 21 × 114 MW (2.4 GW)Market context
08 · Market context — US Data Center Atlas

Southern Virginia: 7 campuses, 5,400 MW tracked

Closest comparables by size: Microsoft Boydton Campus (Azure East US) (1,100 MW); Google Botetourt County (300 (est.) MW).

CampusOperatorStatusMWGC
STACK Southern Virginia Megasite (Berry Hill)STACK InfrastructurePlanned3,000—
Microsoft Boydton Campus (Azure East US)MicrosoftOperational1,100—
Microsoft Panhandle Road ExpansionMicrosoftPlanned300 (est.)—
Microsoft AVC17 LakesideMicrosoftPlanned300 (est.)—
Google Botetourt CountyGoogleUnder construction300 (est.)—
Microsoft Tunstall RoadMicrosoftPlanned200 (est.)—
Ringgold Campus (Route 58 East)Anchorstone AdvisorsPlanned200—

General contractors active elsewhere in VA

Clark Construction, DPR Construction, HITT Contracting

Contested-site flags

None recorded in this market or state.

Developer portfolios (Beale, Related Digital, 5C)

None recorded in this state.

US Data Center Atlas (compiled October 18, 2026, updated November 16), capitolcm.com/atlas. Compiled from public reporting — status, MW (est. = estimated) and GC roles can lag; nothing here is verified or owner data.
© 2026 Frank Fernandez · Developer Program Planner developed for Capitol Construction Management · capitolcm.com  |  Sample report — concept program, not a real project · Concept estimate (AACE Class 4) · Not a quote10
Capitol/CMSample report · Developer Program Planner · Concept Hyperscale Program — 21 × 114 MW (2.4 GW)Basis
Basis

Basis, assumptions and definitions

Classification

Concept estimate consistent with AACE International Class 4 (typical accuracy −15% to −30% / +20% to +50%). Building 1 is priced with the Programmatic Builder engine, validated within ±2% of the Concept Data Center workbook; this report runs the same engine as the Developer Program Planner, so its figures match the web tool for the same inputs.

Program method

  • Buildings 2+ = (site directs × 0.80 + building directs) × 1.00 repetition, plus percentage indirects, plus General Conditions × 1.00; preconstruction fee on Building 1 only.
  • Each building is escalated at 4%/yr from the Nov 2026 pricing basis to its construction midpoint and spent on an S-curve over 20 months.
  • Soft costs as % of construction: design 5%, owner's PM 1.5%, commissioning 0.75%, permits 1%, legal & financing 1%; owner contingency 5% excluding land.
  • Craft follows a trapezoid ramp per building (30% up, 40% plateau, 30% down). GC roster uses the template salary ladder (GS / PX / SPM $350K / $300K / $225K at 1.62 burden), scaled to the Builder's General Conditions. Owner team: 8 program roles + 4.0 FTE per active building + 1 buyer per 3.
  • Yield on cost uses placeholder underwriting inputs (lease $140/kW-month, NOI margin 80%) — not market data.

KPI definitions

S/V = General Conditions ÷ construction volume. ROS = fee ÷ volume. E/V = major electrical and cooling equipment ÷ volume. Safety ratio = peak craft ÷ safety professionals.

Exclusions

Tenant IT equipment (servers, racks, network); financing costs beyond the legal & financing allowance; sales and use tax; prevailing-wage requirements; hazardous materials; rock excavation; campus infrastructure and land unless entered as inputs.

Unit prices, lead times, location factors, escalation and soft-cost rates are planning assumptions — not quotes, owner data or commitments. Confirm with the owner, design team and authority having jurisdiction before relying on these figures for a funding or contracting decision.

Prepared by

Frank Fernandez · Owner's Representation · Mission Critical
Capitol Construction Management · capitolcm.com

Developer Program Planner is proprietary to Frank Fernandez, developed for Capitol Construction Management. © 2026 Frank Fernandez. Sample report — illustrates a concept program; not a real project.

© 2026 Frank Fernandez · Developer Program Planner developed for Capitol Construction Management · capitolcm.com  |  Sample report — concept program, not a real project · Concept estimate (AACE Class 4) · Not a quote11

Sample report — concept program, not a real project · Concept estimate (AACE Class 4) · Not a quote · © 2026 Frank Fernandez · Capitol Construction Management · capitolcm.com