Concept Hyperscale Program — 21 × 114 MW (2.4 GW)
$34.21B to deliver 2,400.3 MW over 12.8 years
21 buildings of 114.3 MW IT in Southside VA, 7 per phase on a 6-month cadence with phases 48 months apart. Building 1 NTP July 2027; last building ready for service March 2040.
What to watch
- Safety coverage: 1 safety professional per 123 craft at 125:1 target; moving to 1:50 adds 19 FTE, about $5.0M per building.
- Long-lead procurement: 4 Building 1 items past the order-by date and 3 to order within 3 months of Nov 19, 2026.
- Peak demand: 3,733 craft and 26 owner FTE at peak; peak quarter spend $995.3M.
- Escalation: 4%/yr from the Nov 2026 basis to each building midpoint adds $7.36B to construction.
Program inputs
| Input | Value | Input | Value |
|---|---|---|---|
| IT load per building | 114.3 MW | Market | Southside VA |
| Buildings / per phase | 21 / 7 | Building 1 NTP | Jul 2027 |
| Cadence / phase offset | 6 / 48 mo | Construction duration | 20 mo |
| Levels / rack density | 2 / 130 kW | Escalation | 4% / yr |
| Generator fuel | Natural gas | Site / repetition / GC factors, bldgs 2+ | 0.80 / 1.00 / 1.00 |
| Fee / contingency | 3.95% / 5% | Campus infrastructure / land | $0 / $0 |
Total development cost $34.21B
Construction is 87% of the total. Building 1 carries the full estimate; buildings 2+ apply the site, repetition and GC factors and are escalated to each construction midpoint.
| Line | Basis | Amount | % of TDC |
|---|---|---|---|
| Construction — all buildings (escalated) | 21 buildings | $29,821,016,235 | 87.2% |
| Design / A&E | 5% of construction | $1,491,050,812 | 4.4% |
| Owner's program management | 1.5% of construction | $447,315,244 | 1.3% |
| Commissioning agent | 0.75% of construction | $223,657,622 | 0.7% |
| Permits & fees | 1% of construction | $298,210,162 | 0.9% |
| Legal & financing | 1% of construction | $298,210,162 | 0.9% |
| Campus infrastructure | input | $0 | 0.0% |
| Land | input | $0 | 0.0% |
| Owner contingency | 5% excl. land | $1,628,973,012 | 4.8% |
| Total development cost | escalated, excl. IT equipment | $34,208,433,249 | 100.0% |
21 buildings in 3 phases, Jul 2027 – Mar 2040
| Bldg | Phase | Start | RFS | Nov 2026 $ | Escalation | Escalated |
|---|---|---|---|---|---|---|
| B1 | 1 | Jul 2027 | Mar 2029 | $1,076.4M | 1.061 | $1,141.6M |
| B2 | 1 | Jan 2028 | Sep 2029 | $1,069.2M | 1.082 | $1,156.5M |
| B3 | 1 | Jul 2028 | Mar 2030 | $1,069.2M | 1.103 | $1,179.4M |
| B4 | 1 | Jan 2029 | Sep 2030 | $1,069.2M | 1.125 | $1,202.7M |
| B5 | 1 | Jul 2029 | Mar 2031 | $1,069.2M | 1.147 | $1,226.6M |
| B6 | 1 | Jan 2030 | Sep 2031 | $1,069.2M | 1.170 | $1,250.8M |
| B7 | 1 | Jul 2030 | Mar 2032 | $1,069.2M | 1.193 | $1,275.6M |
| B8 | 2 | Jul 2031 | Mar 2033 | $1,069.2M | 1.241 | $1,326.6M |
| B9 | 2 | Jan 2032 | Sep 2033 | $1,069.2M | 1.265 | $1,352.9M |
| B10 | 2 | Jul 2032 | Mar 2034 | $1,069.2M | 1.290 | $1,379.7M |
| B11 | 2 | Jan 2033 | Sep 2034 | $1,069.2M | 1.316 | $1,407.0M |
| B12 | 2 | Jul 2033 | Mar 2035 | $1,069.2M | 1.342 | $1,434.9M |
| B13 | 2 | Jan 2034 | Sep 2035 | $1,069.2M | 1.369 | $1,463.3M |
| B14 | 2 | Jul 2034 | Mar 2036 | $1,069.2M | 1.396 | $1,492.3M |
| B15 | 3 | Jul 2035 | Mar 2037 | $1,069.2M | 1.451 | $1,552.0M |
| B16 | 3 | Jan 2036 | Sep 2037 | $1,069.2M | 1.480 | $1,582.7M |
| B17 | 3 | Jul 2036 | Mar 2038 | $1,069.2M | 1.510 | $1,614.1M |
| B18 | 3 | Jan 2037 | Sep 2038 | $1,069.2M | 1.539 | $1,646.0M |
| B19 | 3 | Jul 2037 | Mar 2039 | $1,069.2M | 1.570 | $1,678.6M |
| B20 | 3 | Jan 2038 | Sep 2039 | $1,069.2M | 1.601 | $1,711.9M |
| B21 | 3 | Jul 2038 | Mar 2040 | $1,069.2M | 1.633 | $1,745.8M |
| Total | $22,460.9M | $29,821.0M |
Building 1: $1,076.4M · $9.42M per MW
114.3 MW IT, 457,200 GSF on 2 levels, 880 racks at 130 kW, 56 × 3 MW blocks with natural gas generators and 87 chillers. Priced in Southside VA with the Programmatic Builder engine.
| Cost group | CSI | Amount | % of total |
|---|---|---|---|
| Site development & utilities | 02 · 31–33 | $22,756,682 | 2.1% |
| Structure & envelope | 03–08 | $96,849,146 | 9.0% |
| Interiors & specialties | 09–14 | $9,217,080 | 0.9% |
| Electrical & generation | 26 | $568,382,491 | 52.8% |
| Mechanical & cooling | 22 · 23 · 25 | $178,052,200 | 16.5% |
| Fire protection & security | 21 · 28 | $15,102,560 | 1.4% |
| Communications | 27 | $8,268,640 | 0.8% |
| Trade directs | $898,628,799 | 83.5% | |
| General Requirements | $25,762,995 | 2.4% | |
| General Conditions | $25,584,320 | 2.4% | |
| Contingency | $46,219,590 | 4.3% | |
| SDI | $8,986,288 | 0.8% | |
| OCIP | $15,077,730 | 1.4% | |
| Other insurance | $5,101,299 | 0.5% | |
| P&P bond | $8,202,888 | 0.8% | |
| Preconstruction fee | $2,000,000 | 0.2% | |
| Fee | $40,825,774 | 3.8% | |
| Building 1 total | $1,076,389,683 | 100.0% |
Owner's-rep KPIs (Planner definitions)
| KPI | Value | Definition |
|---|---|---|
| S/V | 2.38% | General Conditions ÷ construction volume |
| ROS | 3.79% | Fee ÷ volume |
| E/V | 52.8% | Major electrical and cooling equipment ÷ volume |
| Safety ratio | 1 : 123 | Peak craft ÷ safety professionals |
| Craft per GC staff / per superintendent | 28.1 / 100 | Peak craft ÷ GC staff; ÷ superintendents |
Spend peaks at $995.3M a quarter; 2038 is the peak year
Program spend by quarter (escalated $, all-in)
Annual spend
| Year | Spend | Cumulative | % of TDC | Starts |
|---|---|---|---|---|
| 2027 | $324.8M | $324.8M | 0.9% | 1 |
| 2028 | $2,248.7M | $2,573.5M | 6.6% | 2 |
| 2029 | $2,730.2M | $5,303.7M | 8.0% | 2 |
| 2030 | $2,839.3M | $8,143.0M | 8.3% | 2 |
| 2031 | $1,888.8M | $10,031.8M | 5.5% | 1 |
| 2032 | $2,642.7M | $12,674.6M | 7.7% | 2 |
| 2033 | $3,193.8M | $15,868.4M | 9.3% | 2 |
| 2034 | $3,321.6M | $19,189.9M | 9.7% | 2 |
| 2035 | $2,209.6M | $21,399.6M | 6.5% | 1 |
| 2036 | $3,091.6M | $24,491.2M | 9.0% | 2 |
| 2037 | $3,736.3M | $28,227.5M | 10.9% | 2 |
| 2038 | $3,885.8M | $32,113.2M | 11.4% | 2 |
| 2039 | $2,068.4M | $34,181.6M | 6.0% | 0 |
| 2040 | $26.8M | $34,208.4M | 0.1% | 0 |
| Total | $34,208.4M | 100.0% | 21 |
Peak 3,733 craft, 173 GC field staff, 26 owner FTE
Program craft headcount
GC staff and owner team
GC roster — Building 1 (57 FTE, $25,584,320)
| Role | Qty | Base | Cost |
|---|---|---|---|
| General Superintendent | 1 | $350K | $1,160,625 |
| Project Executive | 1 | $300K | $994,821 |
| Senior Project Manager | 1 | $225K | $746,116 |
| Project Manager | 2 | $185K | $1,226,946 |
| Assistant Project Manager | 3 | $135K | $1,275,858 |
| Area Superintendent | 8 | $200K | $4,775,143 |
| Assistant Superintendent | 5 | $150K | $2,113,996 |
| MEP Superintendent | 2 | $190K | $1,071,091 |
| MEP Coordinator | 3 | $170K | $1,352,957 |
| Project Engineer | 6 | $110K | $2,079,177 |
| Safety Manager | 1 | $160K | $530,571 |
| Safety Specialist | 12 | $105K | $3,551,512 |
| QA/QC Manager | 2 | $160K | $955,029 |
| Scheduler | 1 | $165K | $547,152 |
| Cost Engineer | 2 | $150K | $994,821 |
| Commissioning Coordinator | 2 | $165K | $547,152 |
| BIM / VDC Manager | 1 | $140K | $371,400 |
| Logistics Manager | 1 | $140K | $394,612 |
| Procurement Manager | 1 | $150K | $397,929 |
| Project Administrator | 2 | $75K | $497,411 |
Owner team
| Program roles (fixed) |
|---|
| Program Executive |
| Development Director |
| Program Controls Lead |
| Procurement / OFCI Lead |
| Utility & Power Lead |
| Entitlements & Permitting Lead |
| EHS Lead |
| Finance & Draw Manager |
| Per active building | FTE |
|---|---|
| Owner's Project Manager | 1 |
| Owner's Construction Manager | 1 |
| Owner's MEP Engineer | 0.5 |
| Commissioning Manager | 0.5 |
| Cost & Schedule Controls | 0.5 |
| Owner QA/QC | 0.5 |
4 past order-by, 3 to order within 3 months — Building 1
Order-by = install month − (on-site buffer + transit + lead time + submittals), from Building 1 NTP Jul 2027. Status date Nov 19, 2026. Later buildings repeat on their own start dates; owner supply agreements should cover the full program quantity.
| ID | Item | Type | Qty | Lead (wks) | Order by | Install | Status |
|---|---|---|---|---|---|---|---|
| U-01 | Utility substation & metering | OFOI | lot | 104 | Oct 2025 | Dec 2027 | Past order-by |
| E-03 | Unit substation transformers 3,750 kVA | OFCI | 56 | 80 | Mar 2026 | Feb 2028 | Past order-by |
| E-01 | Generators | OFCI | 56 | 80 | Apr 2026 | Feb 2028 | Past order-by |
| E-02 | MV switchgear 34.5 kV | OFCI | lot | 70 | Jul 2026 | Mar 2028 | Past order-by |
| U-02 | Natural gas service & meter set | OFOI | lot | 40 | Nov 2026 | Oct 2027 | Order within 3 mo |
| M-01 | Air-cooled chillers 500 t | OFCI | 87 | 44 | Dec 2026 | Feb 2028 | Order within 3 mo |
| E-04 | LV switchboards / paralleling gear | OFCI | lot | 45 | Jan 2027 | Mar 2028 | Order within 3 mo |
| S-01 | Structural steel | CFCI | lot | 16 | Feb 2027 | Sep 2027 | Order before NTP |
| E-05 | UPS modules | OFCI | lot | 36 | Apr 2027 | Apr 2028 | Order before NTP |
| M-02 | CDUs (liquid cooling) | OFCI | 52 | 32 | Jun 2027 | Apr 2028 | Order before NTP |
| S-03 | Freight elevators | CFCI | lot | 40 | Jun 2027 | Jun 2028 | Order before NTP |
Program exposure — buildings already inside each item's lead time
| Equipment | Bldgs past order-by | First on-time building | Its order-by |
|---|---|---|---|
| Utility substation & metering | 3 bldgs | B4 | Apr 2027 |
| Unit substation transformers 3,750 kVA | 2 bldgs | B3 | Mar 2027 |
| Generators | 2 bldgs | B3 | Apr 2027 |
| MV switchgear 34.5 kV | 1 bldgs | B2 | Jan 2027 |
| Natural gas service & meter set | 0 | B1 | Nov 2026 |
| Air-cooled chillers 500 t | 0 | B1 | Dec 2026 |
| LV switchboards / paralleling gear | 0 | B1 | Jan 2027 |
| Structural steel | 0 | B1 | Feb 2027 |
| UPS modules | 0 | B1 | Apr 2027 |
| CDUs (liquid cooling) | 0 | B1 | Jun 2027 |
| Freight elevators | 0 | B1 | Jun 2027 |
Program quantities: 1,176 generators · 1,176 unit substations · 1,827 chillers · 1,092 CDUs.
The same program in 14 markets
Every market re-priced with the same inputs — only labor, material and seismic factors change. Order-of-magnitude reference; location factors are planning assumptions, not quotes.
| Market | Electrician $/hr | Building 1 | B1 $/MW | TDC | TDC $/MW |
|---|---|---|---|---|---|
| Southside VA | $26.35 | $1,076M | $9.42M | $34.21B | $14.25M |
| Atlanta, GA | $27.75 | $1,092M | $9.56M | $34.71B | $14.46M |
| Dallas–Fort Worth, TX | $28.56 | $1,101M | $9.64M | $35.00B | $14.58M |
| Dallas, TX (city / Dallas–Plano–Irving) | $29.71 | $1,114M | $9.75M | $35.41B | $14.75M |
| Tucson, AZ (Pima County) | $29.37 | $1,118M | $9.78M | $35.53B | $14.80M |
| Phoenix, AZ | $30.22 | $1,127M | $9.86M | $35.83B | $14.93M |
| Columbus, OH | $31.11 | $1,130M | $9.89M | $35.91B | $14.96M |
| Las Vegas / Reno, NV | $30.45 | $1,156M | $10.11M | $36.72B | $15.30M |
| Salt Lake City, UT | $30.82 | $1,178M | $10.31M | $37.43B | $15.59M |
| New York / NJ | $38.75 | $1,253M | $10.96M | $39.83B | $16.59M |
| Northern Virginia (Ashburn) | $41.68 | $1,256M | $10.99M | $39.93B | $16.64M |
| Portland / Hillsboro, OR | $42.85 | $1,326M | $11.60M | $42.13B | $17.55M |
| Chicago, IL | $49.00 | $1,346M | $11.78M | $42.79B | $17.83M |
| Silicon Valley (San Jose), CA | $48.55 | $1,408M | $12.31M | $44.73B | $18.64M |
Southern Virginia: 7 campuses, 5,400 MW tracked
Closest comparables by size: Microsoft Boydton Campus (Azure East US) (1,100 MW); Google Botetourt County (300 (est.) MW).
| Campus | Operator | Status | MW | GC |
|---|---|---|---|---|
| STACK Southern Virginia Megasite (Berry Hill) | STACK Infrastructure | Planned | 3,000 | — |
| Microsoft Boydton Campus (Azure East US) | Microsoft | Operational | 1,100 | — |
| Microsoft Panhandle Road Expansion | Microsoft | Planned | 300 (est.) | — |
| Microsoft AVC17 Lakeside | Microsoft | Planned | 300 (est.) | — |
| Google Botetourt County | Under construction | 300 (est.) | — | |
| Microsoft Tunstall Road | Microsoft | Planned | 200 (est.) | — |
| Ringgold Campus (Route 58 East) | Anchorstone Advisors | Planned | 200 | — |
General contractors active elsewhere in VA
Clark Construction, DPR Construction, HITT Contracting
Contested-site flags
None recorded in this market or state.
Developer portfolios (Beale, Related Digital, 5C)
None recorded in this state.
Basis, assumptions and definitions
Classification
Concept estimate consistent with AACE International Class 4 (typical accuracy −15% to −30% / +20% to +50%). Building 1 is priced with the Programmatic Builder engine, validated within ±2% of the Concept Data Center workbook; this report runs the same engine as the Developer Program Planner, so its figures match the web tool for the same inputs.
Program method
- Buildings 2+ = (site directs × 0.80 + building directs) × 1.00 repetition, plus percentage indirects, plus General Conditions × 1.00; preconstruction fee on Building 1 only.
- Each building is escalated at 4%/yr from the Nov 2026 pricing basis to its construction midpoint and spent on an S-curve over 20 months.
- Soft costs as % of construction: design 5%, owner's PM 1.5%, commissioning 0.75%, permits 1%, legal & financing 1%; owner contingency 5% excluding land.
- Craft follows a trapezoid ramp per building (30% up, 40% plateau, 30% down). GC roster uses the template salary ladder (GS / PX / SPM $350K / $300K / $225K at 1.62 burden), scaled to the Builder's General Conditions. Owner team: 8 program roles + 4.0 FTE per active building + 1 buyer per 3.
- Yield on cost uses placeholder underwriting inputs (lease $140/kW-month, NOI margin 80%) — not market data.
KPI definitions
S/V = General Conditions ÷ construction volume. ROS = fee ÷ volume. E/V = major electrical and cooling equipment ÷ volume. Safety ratio = peak craft ÷ safety professionals.
Exclusions
Tenant IT equipment (servers, racks, network); financing costs beyond the legal & financing allowance; sales and use tax; prevailing-wage requirements; hazardous materials; rock excavation; campus infrastructure and land unless entered as inputs.
Prepared by
Frank Fernandez · Owner's Representation · Mission Critical